7067 W MANCHESTER AVE 90045
Certificate Information: 7067 W MANCHESTER AVE 90045
- Application / Permit
- 25016-10000-02762
- Plan Check / Job No.
- B25LA03679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding a DBL Hardy Frame HFX panel at North Elevation
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Current Status
- Issued on 4/7/2025
Permit Application Status History
| Submitted | 1/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | HANS SANTIAGO |
| Corrections Issued | 2/10/2025 | HANS SANTIAGO |
| Quality Review Completed | 2/20/2025 | DANIEL CHAN |
| Plan Check Approved | 3/14/2025 | ANDREW SANTIAGO |
| Issued | 4/7/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/7/2025 | KORNEL LELEA |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | , |
| Contractor | Sks Construction; Lic. No.: 720390-B | , |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 15134 FRIAR ST VAN NUYS, CA 91411 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/1/2025 | Approved | RICARDO ROBLES |
| Deputy Drilled-In Anchors | 5/9/2025 | Conditional Approval | RICARDO ROBLES |
| Footing/Foundation/Slab | 5/13/2025 | Approved | RICARDO ROBLES |
| Deputy Reinf. Concrete | 5/20/2025 | Conditional Approval | RICARDO ROBLES |
| Wood Frame | 6/18/2025 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 6/24/2025 | Approved | DERRICK SPENCER |
| Final | 8/28/2025 | Partial Inspection | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | DAVID TSAU |
| Smoke Detectors | 8/28/2025 | No Access for Inspection | DAVID TSAU |
| Final | 11/20/2025 | Partial Approval | RICARDO ROBLES |
| Smoke Detectors | 11/20/2025 | Approved | RICARDO ROBLES |