6048 S MADDEN AVE 90043
Certificate Information: 6048 S MADDEN AVE 90043
- Application / Permit
- 25016-10000-02448
- Plan Check / Job No.
- B25LA03185
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) . ALL WORK PER WFPP
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Current Status
- CofO Issued on 8/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 2/1/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 2/14/2025 | KEVIN MORALES |
| Issued | 2/14/2025 | APPLICANT |
| CofO in Progress | 8/24/2025 | WAYNE REGESTER |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| CofO Issued | 8/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2025 | DAVID VO |
| Sewer availability | Cleared | 2/6/2025 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2025 | DAVID VO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/11/2025 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 3/11/2025 | Partial Approval | MICHAEL LEWIS |
| Sewer | 3/11/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 3/11/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/13/2025 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 5/8/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 5/8/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 5/8/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 5/8/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 5/13/2025 | Approved | WAYNE REGESTER |
| Insulation | 5/13/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 5/19/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 5/19/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 6/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 6/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 6/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 6/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Final | 6/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Service/Power Release | 6/18/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 6/18/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 7/22/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 7/22/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 7/22/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 7/22/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 7/22/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 7/29/2025 | Approved | WAYNE REGESTER |
| Final | 7/29/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Approved | WAYNE REGESTER |
| Final | 8/20/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 8/22/2025 | OK to Issue CofO | WAYNE REGESTER |