633 E CALIFORNIA AVE 90291
Certificate Information: 633 E CALIFORNIA AVE 90291
- Application / Permit
- 25016-10000-02374
- Plan Check / Job No.
- B25LA03063
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. Major remodel to single family dwelling and foundation to remain. New framing, windows, doors. NFPA 13D all throughout.
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Current Status
- Issued on 5/29/2025
Permit Application Status History
| Submitted | 1/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2025 | ALEXANDER JOO |
| Corrections Issued | 2/13/2025 | ALEXANDER JOO |
| Quality Review Completed | 2/13/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 3/24/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 5/1/2025 | ALEXANDER JOO |
| Applicant returned to address corrections | 5/22/2025 | ALEXANDER JOO |
| Plan Check Approved | 5/29/2025 | ALEXANDER JOO |
| Issued | 5/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2025 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2025 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 3/17/2025 | JUSTIN BICOL |
| Sewer availability | Cleared | 3/17/2025 | JUSTIN BICOL |
| Hydrant and Access approval | Cleared | 3/18/2025 | PATRICK PEREZ |
| Coastal Zone | Cleared | 3/19/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 3/19/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 3/19/2025 | DANIEL CORONADO |
| Miscellaneous | Cleared | 3/19/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 3/19/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 3/20/2025 | LUIS LOPEZ |
| Specific Plan | Cleared | 4/23/2025 | PEDRO AYALA |
Contact Information
| Architect | , ; Lic. No.: C37727 | , |
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/31/2025 | Partial Approval | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 1/27/2026 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | No Access for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/2/2026 | Approved | MICHAEL ALLEN |
| Gas Test | 3/2/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 3/2/2026 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 3/2/2026 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 3/12/2026 | Approved | RUBEN RIVAS |
| Deputy Wood Construction | 3/24/2026 | Conditional Approval | DAVID FEILER |
| HVAC-Rough | 3/25/2026 | Corrections Issued | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 3/26/2026 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/27/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | RUBEN RIVAS |
| Shower Pan | 4/15/2026 | Approved | RUBEN RIVAS |
| Insulation | 4/17/2026 | No Access for Inspection | MICHAEL ALLEN |
| Insulation | 4/21/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 4/28/2026 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 5/1/2026 | Approved | RUBEN RIVAS |
| Grading Pre-Inspection | 6/4/2026 | No Result Entered | RUBEN RIVAS |