5322 W 82ND ST 90045
Certificate Information: 5322 W 82ND ST 90045
- Application / Permit
- 25016-10000-02220
- Plan Check / Job No.
- B25LA02846
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING DETACHED GARAGE INTO ADU PER GCS 66323(a)(1). ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/17/2025
- Issuing Office
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | MINA HABILI |
| Corrections Issued | 1/31/2025 | MINA HABILI |
| Building Plans Picked Up | 2/7/2025 | APPLICANT |
| Plan Check Approved | 4/16/2025 | JOSE VELAZQUEZ |
| Issued | 4/17/2025 | APPLICANT |
| CofO in Progress | 1/8/2026 | JESUS PINEDA |
| Permit Finaled | 1/8/2026 | RICHARD STEINBACH |
| CofO Issued | 1/8/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/8/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/21/2025 | ALEXANDER HELFER |
| Address approval | Cleared | 2/22/2025 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 2/22/2025 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | JOSE HERNANDEZ |
| Construction within easement | Cleared | 4/3/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Ornelas F Construction; Lic. No.: 784289-B | P O BOX 922735 SYLMAR, CA 91392 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2025 | Partial Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 6/12/2025 | Approved | JESUS PINEDA |
| Special/Order Compliance | 6/12/2025 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Rough | 8/6/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 8/6/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 8/6/2025 | Approved | JESUS PINEDA |
| Sewer | 8/6/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 8/6/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/15/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 8/22/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 8/22/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/22/2025 | Partial Approval | JESUS PINEDA |
| Insulation | 9/2/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 9/12/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/30/2025 | Approved | JESUS PINEDA |
| Shower Pan | 9/30/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 12/8/2025 | Approved | JESUS PINEDA |
| Final | 12/8/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 12/8/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 12/8/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 12/8/2025 | Approved | JESUS PINEDA |
| Final | 1/7/2026 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 1/7/2026 | Approved | JESUS PINEDA |