4216 S 3RD AVE 90008
Certificate Information: 4216 S 3RD AVE 90008
- Application / Permit
- 25016-10000-02034
- Plan Check / Job No.
- B25LA02601
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED GARAGE INTO ADU PER GC 66323(a)(1). ALL WORK PER ENGINEER
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2025 | JOHNPAUL ISIP |
| Corrections Issued | 2/12/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 4/7/2025 | JOHNPAUL ISIP |
| Issued | 5/19/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | LUIS CASTRO |
| CofO Issued | 4/23/2026 | DEROLD HAUFF |
| Permit Finaled | 4/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/22/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Artisan & Co; Lic. No.: 1115180-B | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | No Access for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/11/2025 | No Access for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 7/11/2025 | No Access for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 7/14/2025 | Corrections Issued | WAYNE REGESTER |
| PLUMBING-Rough | 7/14/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Rough | 7/23/2025 | Not Ready for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 7/23/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 7/23/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 8/5/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 8/5/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/12/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 8/12/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 8/12/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/9/2025 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 9/9/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 9/9/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 9/9/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 9/9/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 9/9/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 10/3/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 10/3/2025 | Approved | LUIS CASTRO |
| Insulation | 10/3/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 10/3/2025 | Partial Approval | LUIS CASTRO |
| Drywall Nailing | 10/9/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/9/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Drywall Nailing | 10/15/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/4/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 4/6/2026 | Approved | LUIS CASTRO |
| Final | 4/6/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/6/2026 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 4/6/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/6/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 4/6/2026 | Approved | LUIS CASTRO |
| Final | 4/20/2026 | OK to Issue CofO | LUIS CASTRO |
| Green Building Final | 4/20/2026 | Approved | LUIS CASTRO |