1604 S ORANGE GROVE AVE 90019
Certificate Information: 1604 S ORANGE GROVE AVE 90019
- Application / Permit
- 25016-10000-01978
- Plan Check / Job No.
- B25LA00626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *Eplan.* Convert detached Garage to ADU per GCS 66323(a)(1).
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | HUAN LE |
| Corrections Issued | 1/23/2025 | HUAN LE |
| Quality Review Completed | 1/27/2025 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 3/13/2025 | HUAN LE |
| Plan Check Approved | 3/18/2025 | HUAN LE |
| Issued | 3/20/2025 | APPLICANT |
| CofO in Progress | 3/17/2026 | BRENDAN MORELLI |
| Permit Finaled | 3/18/2026 | DEROLD HAUFF |
| CofO Issued | 3/18/2026 | DEROLD HAUFF |
| Permit Finaled | 3/18/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 2/18/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/18/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 3/4/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/1/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 7/1/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Rough | 7/1/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/3/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 7/3/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 7/3/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 7/9/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 7/22/2025 | Partial Approval | ARTHUR NEGRETE |
| Green Building Rough | 7/22/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 7/22/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 8/4/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 12/3/2025 | Approved | BRENDAN MORELLI |
| Final | 12/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 12/3/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/3/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Service/Power Release | 12/3/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 12/3/2025 | Approved | BRENDAN MORELLI |
| Final | 12/29/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Service/Power Release | 12/29/2025 | Approved | BRENDAN MORELLI |
| Final | 3/3/2026 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 3/3/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Approved | BRENDAN MORELLI |
| Final | 3/13/2026 | OK to Issue CofO | BRENDAN MORELLI |