984 N BEL-AIR ROAD 90077
Certificate Information: 984 N BEL-AIR ROAD 90077
- Application / Permit
- 25016-10000-01785
- Plan Check / Job No.
- B25LA02260
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SCOPE OF WORK CONSIST OF RENOVATING THE EXISTING SINGLE-FAMILY, ADDITION TO (E) SFD TO CONNECT SFD TO GARAGE AND EXTENDING THE BALCONY
- Permit Issued
- Issued on 10/16/2025
- Issuing Office
- Metro
- Current Status
- Issued on 10/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | VARAND SARKISIAN |
| Corrections Issued | 1/28/2025 | VARAND SARKISIAN |
| Quality Review Completed | 1/29/2025 | KEN GILL |
| Building Plans Picked Up | 2/18/2025 | APPLICANT |
| Plan Check Approved | 8/28/2025 | VARAND SARKISIAN |
| Issued | 10/16/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/6/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 6/6/2025 | KIMBERLY HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 6/6/2025 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2025 | KIMBERLY HERNANDEZ |
| ZI | Cleared | 6/10/2025 | BRENNEN OBETO |
| Grading Pre-Inspection | Cleared | 6/16/2025 | JONATHAN HOM |
| Roof/Waste drainage to street | Cleared | 6/20/2025 | LIAM ODONOVAN |
| BHO/Hillside ordinance | Cleared | 7/15/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 7/15/2025 | RYAN CASTRO |
| BHO/Hillside ordinance | Cleared | 7/23/2025 | JESUS CISNEROS |
Contact Information
| Contractor | Supreme Remodeling Inc; Lic. No.: 939981-B | 14545 VICTORY BLVD UNIT 401 VAN NUYS, CA 91411 |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 16526 BLACKHAWK ST GRANADA HILLS, CA 91344 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2025 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 11/26/2025 | Corrections Issued | SEAN HAUPT |
| Deputy Reinf. Masonry | 6/25/2026 | Conditional Approval | RYAN SALAZAR |
| Masonry Wall/Backfill | 7/2/2026 | Partial Approval | RYAN SALAZAR |
| Deputy Reinf. Concrete | 7/21/2026 | Conditional Approval | ANDREW NAVE |
| Reinforced Masonry Frame | 7/22/2026 | Partial Approval | EVAN COOPER |