8039 S DUNFIELD AVE 90045
Certificate Information: 8039 S DUNFIELD AVE 90045
- Application / Permit
- 25016-10000-01646
- Plan Check / Job No.
- B25LA02048
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Convert existing detached garage to an ADU per LAMC 12.22 A.33(b)(1). All work per EOR
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- Current Status
- CofO Issued on 1/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2025 | DANIEL SANJUAN |
| Corrections Issued | 1/27/2025 | DANIEL SANJUAN |
| Plan Check Approved | 2/9/2025 | DANIEL SANJUAN |
| Issued | 4/2/2025 | APPLICANT |
| CofO in Progress | 1/14/2026 | ANTHONY EGSON |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
| CofO Issued | 1/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/27/2025 | RIDWAN HARDY |
| Address approval | Cleared | 2/3/2025 | DARIN LAM |
| Sewer availability | Cleared | 2/3/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2025 | DARIN LAM |
| Specific Plan | Cleared | 2/6/2025 | FREDDY GARCIA |
Contact Information
| Contractor | Nittay Inc; Lic. No.: 1033506-B | , |
| Contractor | P M A Renovations; Lic. No.: 1033506-B | , |
| Engineer | Fleming,, Michael Andrew; Lic. No.: C22979 | 15428 SEQUOIA GROVE AVE BAKERSFIELD, CA 93314 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 7/10/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 7/14/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 7/14/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 7/14/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 7/14/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 7/17/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 7/17/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 7/17/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 7/23/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Shower Pan | 7/24/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Shower Pan | 7/25/2025 | Approved | RUBEN RIVAS |
| Insulation | 7/28/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 7/28/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 8/4/2025 | Approved | MICHAEL ALLEN |
| Final | 1/7/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 1/7/2026 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/7/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/13/2026 | Approved | ANTHONY EGSON |
| Final | 1/13/2026 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 1/13/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/13/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/13/2026 | Approved | ANTHONY EGSON |