25701 S PRESIDENT AVE 90710

Certificate Information: 25701 S PRESIDENT AVE 90710

Application / Permit
25016-10000-01569
Plan Check / Job No.
B25LA01939
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Using plywood shear walls
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
CofC Issued on 11/19/2025

Permit Application Status History

Submitted 2/5/2025 APPLICANT
Assigned to Plan Check Engineer 2/13/2025 HANS SANTIAGO
Corrections Issued 2/17/2025 HANS SANTIAGO
Quality Review Completed 2/26/2025 DANIEL CHAN
Applicant returned to address corrections 4/23/2025 HANS SANTIAGO
Plan Check Approved 4/30/2025 ANDREW SANTIAGO
Issued 7/14/2025 APPLICANT
OK for CofC 11/17/2025 JOEY BUCHANAN
CofC Issued 11/19/2025 DAVID TSAU

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/14/2025 KORNEL LELEA

Contact Information

Contractor Bay Cities Construction; Lic. No.: 842614-B       ,
Contractor Property Assistance Inc; Lic. No.: 842614-B       ,
Engineer Bell,, William; Lic. No.: C88870 550 DEEP VALLEY DR STE 273      ROLLING HILLS ESTATES, CA 90274

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2025 Partial Approval RICARDO ROBLES
Excavation/Setback/Form/Re-Bar 8/1/2025 Approved RICARDO ROBLES
Footing/Foundation/Slab 8/1/2025 Approved RICARDO ROBLES
Wall Anchors 8/1/2025 Approved RICARDO ROBLES
Wood Frame 8/1/2025 Partial Inspection RICARDO ROBLES
Wood Frame 8/8/2025 Partial Inspection RICARDO ROBLES
Deputy Wood Construction 8/11/2025 Conditional Approval RICARDO ROBLES
Floor/Roof Diaphrgm/Shear Wall 8/11/2025 Partial Approval RICARDO ROBLES
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Approved MICHAEL PETRUSKO
Interior/Exterior Lathing 8/15/2025 Approved RICARDO ROBLES
Final 9/19/2025 No Access for Inspection MICHAEL PETRUSKO
METHANE-Final 9/19/2025 Not Ready for Inspection MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 9/19/2025 SGSOV Not Ready MICHAEL PETRUSKO
Smoke Detectors 9/19/2025 Not Ready for Inspection MICHAEL PETRUSKO
Final 10/3/2025 Not Ready for Inspection MICHAEL PETRUSKO
METHANE-Final 10/3/2025 Not Ready for Inspection MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Not Ready MICHAEL PETRUSKO
Smoke Detectors 10/3/2025 Not Ready for Inspection MICHAEL PETRUSKO
Final 10/9/2025 Conditional Approval MICHAEL PETRUSKO
METHANE-Final 10/9/2025 Approved MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved MICHAEL PETRUSKO
Smoke Detectors 10/9/2025 Approved MICHAEL PETRUSKO
Final 11/17/2025 OK for CofC JOEY BUCHANAN