2326 3/4 S PENMAR AVE 90291
Certificate Information: 2326 3/4 S PENMAR AVE 90291
- Application / Permit
- 25016-10000-01244
- Plan Check / Job No.
- B25LA01595
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 18'-3"X16'-2" GARAGE AND 8'-8"X1'-10" UNPERMITTED PORTION BUILT PRIOR TO JAN 1, 2018 PER GCS 65852.23 TO ACCESSORY DWELLING UNIT PER STATE LAW (GCS 66323(a)(1)) AND IB P/BC 2023-150. Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/25/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/27/2025 | APPLICANT |
| Applicant returned to address corrections | 3/14/2025 | DAVID CASTILLO |
| Issued | 4/3/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/29/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2025 | RYAN CASTRO |
| Specific Plan | Cleared | 2/4/2025 | FREDDY GARCIA |
| "Q" conditions | Cleared | 2/7/2025 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/29/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Partial Approval | MICHAEL ALLEN |
| Green Building Final | 8/6/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Green Building Rough | 8/6/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Not Ready | MICHAEL ALLEN |
| Smoke Detectors | 8/6/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 8/6/2025 | Corrections Issued | MICHAEL ALLEN |
| Pre-Inspection | 8/13/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/13/2025 | Partial Inspection | DAVID FEILER |
| Special/Order Compliance | 8/13/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Pre-Inspection | 12/4/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 12/10/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 12/11/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 12/17/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Not Ready | RUBEN RIVAS |
| ELECTRICAL-Rough | 1/15/2026 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Final | 3/24/2026 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 4/14/2026 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 7/2/2026 | Approved | RUBEN RIVAS |
| Final | 7/2/2026 | Partial Approval | RUBEN RIVAS |
| Green Building Final | 7/2/2026 | Approved | RUBEN RIVAS |
| Green Building Rough | 7/2/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 7/2/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2026 | SGSOV Approved | RUBEN RIVAS |
| Final | 7/14/2026 | Corrections Issued | RUBEN RIVAS |