1298 W 35TH PL 90007
Certificate Information: 1298 W 35TH PL 90007
- Application / Permit
- 25016-10000-01192
- Plan Check / Job No.
- B25LA01500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story Seismic Retrofit per LABC Chapter 93: SOFT STORY RETROFIT AT OPEN FRONT PARKING GARAGE (ADD NEW (1) SPECIAL CANTILEVERED COLUMN)
- Permit Issued
- Issued on 5/8/2025
- Issuing Office
- Current Status
- CofC Issued on 2/2/2026
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | BIDYUT RATH |
| Corrections Issued | 1/28/2025 | BIDYUT RATH |
| Quality Review Completed | 2/5/2025 | HANS SANTIAGO |
| Applicant returned to address corrections | 4/2/2025 | BIDYUT RATH |
| Plan Check Approved | 4/7/2025 | BIDYUT RATH |
| Issued | 5/8/2025 | APPLICANT |
| OK for CofC | 2/2/2026 | DARRYL ARNOLD |
| CofC Issued | 2/2/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 3/25/2025 | JACQUELINE TORRES |
| Community Plan Implem. Overlay | Cleared | 4/5/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2025 | JESSICA OPINION |
| Tenant Habitability Plan | Cleared | 5/5/2025 | KORNEL LELEA |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Wu,, Shu; Lic. No.: NA90391 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/18/2025 | Approved | DARRYL ARNOLD |
| Wood Frame | 6/18/2025 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 6/24/2025 | Approved | DARRYL ARNOLD |
| Final | 7/11/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 7/11/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 7/11/2025 | Approved | DARRYL ARNOLD |
| Final | 2/2/2026 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 2/2/2026 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | DARRYL ARNOLD |