10644 W LE CONTE AVE 90024
Certificate Information: 10644 W LE CONTE AVE 90024
- Application / Permit
- 25016-10000-01071
- Plan Check / Job No.
- B25LA01342
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED INTERIOR REMODELING TO REMOVE BEARING WALL AT KITCHEN BETWEEN BAR, DINING, REMODEL KITCHEN AND ADD ISLAND, REMODEL 3 BATH AND POWDER ROOM.
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/17/2026
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2025 | ZAW HAN |
| Plan Check Approved | 1/23/2025 | ZAW HAN |
| Issued | 1/27/2025 | APPLICANT |
| Permit Finaled | 3/16/2026 | EVAN COOPER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Ene Builders; Lic. No.: 1113906-B | 21434 WYANDOTTE STREET CANOGA PARK, CA 91303 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/6/2025 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 2/12/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 2/18/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/7/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 4/7/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 4/7/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 4/10/2025 | Approved | DANIEL VERA |
| PLUMBING-Rough | 4/10/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 4/14/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/16/2025 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 4/16/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 4/17/2025 | Not Ready for Inspection | DANIEL VERA |
| Wood Frame | 4/17/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | DANIEL VERA |
| Green Building Rough | 5/2/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 5/2/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 5/2/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 5/13/2025 | Partial Approval | SEAN HAUPT |
| Drywall Nailing | 5/27/2025 | Approved | STEPHANIE SWANSON |
| Final | 3/16/2026 | Permit Finaled | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 3/16/2026 | Approved | EVAN COOPER |
| Smoke Detectors | 3/16/2026 | Approved | EVAN COOPER |