14823 W CALIFA ST UINT B 91411
Certificate Information: 14823 W CALIFA ST UINT B 91411
- Application / Permit
- 25016-10000-01069
- Plan Check / Job No.
- B25LA01335
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT WORK ON 7,812 SQ.FT OF THE TOTAL FLOOR AREA. NEW WALL, POWER, LIGHTING AND FINISHES. NO CHANGE IN PARKING.
- Permit Issued
- Issued on 3/26/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/10/2025
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2025 | JOSE VELAZQUEZ |
| Plan Check Approved | 1/15/2025 | JOSE VELAZQUEZ |
| Issued | 3/26/2025 | APPLICANT |
| Permit Finaled | 9/9/2025 | BRIAN KELLY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | Keane Constructors Inc; Lic. No.: 532966-B | 29021 AVENUE SHERMAN UNIT 105 VALENCIA, CA 91355 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2025 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 5/14/2025 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 5/27/2025 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 5/29/2025 | Partial Approval | BRIAN KELLY |
| Light Gage Steel Frame | 6/4/2025 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 6/6/2025 | Partial Approval | BRIAN KELLY |
| Light Gage Steel Frame | 7/21/2025 | Partial Inspection | BRIAN KELLY |
| Drywall Nailing | 7/28/2025 | Approved | BRIAN KELLY |
| T-Bar Ceiling | 8/6/2025 | Corrections Issued | DEANDRE HOFFMAN |
| T-Bar Ceiling | 8/7/2025 | Approved | BRIAN KELLY |
| Final | 8/22/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 8/22/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 9/9/2025 | Permit Finaled | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 9/9/2025 | Approved | BRIAN KELLY |