818 S SPRING ST #117 90014

Certificate Information: 818 S SPRING ST #117 90014

Application / Permit
25016-10000-00941
Plan Check / Job No.
B25LA01139
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Massage Parlor
Work Description
CHANGE OF USE FROM RETAIL TO MASSAGE PARLOR NEW INTERIOR NON LOAD BEARING PARTITIONS WHERE ANY PERSON WHO PROVIDES MASSAGE SERVICE AT THIS PREMISE SHALL BE CERTIFIED AS A MASSAGE THERAPIST OR MASSAGE PRACTITIONER PURSUANT TO CALIFORNIA BUSINESS AND PROFESSIONS SECTION 4600 ET ESQ.
Permit Issued
Issued on 3/21/2025
Issuing Office
Metro
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/17/2025 ZAW HAN
Corrections Issued 1/21/2025 ZAW HAN
Building Plans Picked Up 1/21/2025 APPLICANT
Applicant returned to address corrections 1/31/2025 LAWRENCE QUIRANTE
Applicant returned to address corrections 2/18/2025 EDWIN MARTINEZ
Plan Check Approved 3/20/2025 GEORGE ALVAREZ
Issued 3/21/2025 APPLICANT
CofO in Progress 8/19/2025 RONALD JIMENEZ
Permit Finaled 8/19/2025 ERNESTO CORRAL
CofO Issued 8/19/2025 ERNESTO CORRAL
Permit Finaled 8/19/2025 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 1/31/2025 JACQUELINE TORRES
CPC Cleared 1/31/2025 JACQUELINE TORRES
CPC Cleared 1/31/2025 JACQUELINE TORRES
Eng Process Fee Ord 176,300 Cleared 3/7/2025 JUSTIN BICOL
Sewer availability Cleared 3/7/2025 JUSTIN BICOL
Historic Resource Verification Cleared 3/18/2025 YASMINE BASHIRI
Redevelopment Project Area Cleared 3/18/2025 YASMINE BASHIRI

Contact Information

Contractor Jiecheng Construction; Lic. No.: 1068257-B 1552 PROSPECT AVE   APT-D    SAN GABRIEL, CA 91776
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 4/1/2025 Partial Approval PAUL BAZERKANIAN
Wood Frame 6/24/2025 Partial Approval PAUL BAZERKANIAN
Final 7/9/2025 Conditional Approval RONALD JIMENEZ
METHANE-Final 7/9/2025 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 7/9/2025 Approved RONALD JIMENEZ
Final 8/19/2025 OK to Issue CofO RONALD JIMENEZ