8531 S FIGUEROA ST 90003

Certificate Information: 8531 S FIGUEROA ST 90003

Application / Permit
25016-10000-00712
Plan Check / Job No.
B24LA38456
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
ePlan. Existing Chruch's Chicken with drive-thru to be converted to Dunkin' donuts. No change is site layout, no change in building square footage.
Permit Issued
Issued on 5/21/2025
Issuing Office
Current Status
Permit Finaled on 3/25/2026

Permit Application Status History

Submitted 1/13/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 SALVADOR QUINTANILLA
Assigned to Zoning Architect 1/16/2025 RONALD GREENE
Corrections Issued 1/18/2025 SALVADOR QUINTANILLA
Quality Review Completed 1/21/2025 PETER KIM
Applicant returned to address corrections 3/25/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 4/2/2025 SALVADOR QUINTANILLA
Plan Check Approved 5/19/2025 SALVADOR QUINTANILLA
Issued 5/21/2025 APPLICANT
Permit Finaled 3/25/2026 DARRYL ARNOLD

Permit Application Clearance Information

DAS Clearance Cleared 1/24/2025 NORLITO MEDRANO
Historic Resource Verification Cleared 3/3/2025 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 3/3/2025 ELIZABETH GALLARDO
Food Service Establishment Cleared 3/11/2025 KENNETH BROWNE
Community Plan Implem. Overlay Cleared 3/19/2025 MANERI ROMAN
Community Plan Implem. Overlay Cleared 3/19/2025 MANERI ROMAN
Green Code Cleared 4/25/2025 Fernando Flores
Zoning Plan Check Cleared 5/15/2025 Ronald Greene
Food establishment approval Cleared 5/19/2025 LACDHS APPROVED

Contact Information

Architect Deppe,, Paul W; Lic. No.: NA28602       ,
Contractor Mitchell General Contractors Inc; Lic. No.: 831334-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/10/2025 Approved DARRYL ARNOLD
Light Gage Steel Frame 6/30/2025 Partial Inspection ALFREDO LOPEZ
Wood Frame 7/1/2025 Partial Approval ALFREDO LOPEZ
Wood Frame 7/3/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 7/8/2025 Partial Approval ALFREDO LOPEZ
Insulation 7/8/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 7/9/2025 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 7/10/2025 Conditional Approval DARRYL ARNOLD
Drywall Nailing 7/14/2025 Approved DARRYL ARNOLD
Drywall Nailing 7/15/2025 Approved DARRYL ARNOLD
Drywall Nailing 7/17/2025 Approved DARRYL ARNOLD
Interior/Exterior Lathing 8/5/2025 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 8/22/2025 Corrections Issued ALFREDO LOPEZ
T-Bar Ceiling 8/25/2025 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 9/5/2025 Approved ALFREDO LOPEZ
T-Bar Ceiling 12/9/2025 Approved LARRY ARNICK
T-Bar Ceiling 12/10/2025 Approved ALFREDO LOPEZ
Final 2/26/2026 Conditional Approval DARRYL ARNOLD
Green Building Final 2/26/2026 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 2/26/2026 Corrections Issued DARRYL ARNOLD
Final 3/17/2026 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 3/17/2026 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/17/2026 Corrections Issued DARRYL ARNOLD
Final 3/25/2026 Permit Finaled DARRYL ARNOLD
Green Building Final 3/25/2026 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/25/2026 SGSOV Not Required DARRYL ARNOLD
Smoke Detectors 3/25/2026 Approved DARRYL ARNOLD