8122 S BELFORD AVE 90045

Certificate Information: 8122 S BELFORD AVE 90045

Application / Permit
25016-10000-00594
Plan Check / Job No.
B25LA00665
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REPAIR/REBUILD DAMAGED PORTION OF EXISTING SFD AND INTERIOR REMODEL. "COMPLY WITH DEPARTMENT ORDER effective date 10/31/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
Permit Finaled on 8/18/2025

Permit Application Status History

Submitted 1/10/2025 APPLICANT
Assigned to Plan Check Engineer 1/14/2025 ISIS ARGUETA
Corrections Issued 1/15/2025 ISIS ARGUETA
Plan Check Approved 2/14/2025 ALEC MOUSAKHANIAN
Issued 3/12/2025 APPLICANT
Permit Finaled 8/15/2025 ANDREW BEELI

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Love Home Renovations; Lic. No.: 1055055-B       ,
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/19/2025 Partial Approval ANDREW BEELI
Pre-Inspection 3/28/2025 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 4/3/2025 Partial Approval ANDREW BEELI
Pre-Inspection 4/3/2025 Approved ANDREW BEELI
BUILDING-Rough-Frame 4/18/2025 Corrections Issued JOHN MATTILLO
Rough-Elec/Plmb/HVAC 4/18/2025 Corrections Issued JOHN MATTILLO
BUILDING-Rough-Frame 4/24/2025 Corrections Issued ANDREW BEELI
ELECTRICAL-Rough 4/24/2025 Not Ready for Inspection ANDREW BEELI
Insulation 5/5/2025 Approved JOHN MATTILLO
Interior/Exterior Lathing 5/5/2025 Partial Approval JOHN MATTILLO
Shower Pan 5/5/2025 Approved JOHN MATTILLO
Drywall Nailing 5/9/2025 Approved ANDREW BEELI
Interior/Exterior Lathing 5/9/2025 Approved ANDREW BEELI
Wood Frame 6/13/2025 Not Ready for Inspection ANDREW BEELI
Final 7/18/2025 Corrections Issued ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 7/18/2025 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 7/18/2025 Approved ANDREW BEELI
Final 8/15/2025 Permit Finaled ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved ANDREW BEELI