7520 N NESTLE AVE 91335
Certificate Information: 7520 N NESTLE AVE 91335
- Application / Permit
- 25016-10000-00543
- Plan Check / Job No.
- B25LA00608
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO ADU PER WFPP (State ADU Types, Conversion of Accessory Structure, GC 66323(a)(1))
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2025 | AUNG SOE |
| Corrections Issued | 1/14/2025 | AUNG SOE |
| Plan Check Approved | 1/29/2025 | AUNG SOE |
| Issued | 2/4/2025 | APPLICANT |
| CofO in Progress | 9/19/2025 | JUAN ALVARADO |
| Permit Finaled | 9/24/2025 | JOHN JANSON |
| CofO Issued | 9/24/2025 | JOHN JANSON |
| Permit Finaled | 9/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/18/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 4/9/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Underground Mechanical | 4/9/2025 | Partial Approval | JUAN ALVARADO |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Partial Approval | JUAN ALVARADO |
| Footing/Foundation/Slab | 4/15/2025 | Partial Approval | JUAN ALVARADO |
| Underground Mechanical | 4/15/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Sewer | 4/17/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Underground Mechanical | 4/17/2025 | Approved | JUAN ALVARADO |
| Sewer | 4/22/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/2/2025 | Partial Approval | JUAN ALVARADO |
| ELECTRICAL-Rough | 6/2/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Approved | JUAN ALVARADO |
| Footing/Foundation/Slab | 6/2/2025 | Approved | JUAN ALVARADO |
| Gas Test | 6/2/2025 | Approved | JUAN ALVARADO |
| HVAC-Rough | 6/2/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 6/2/2025 | Approved | JUAN ALVARADO |
| Rough-Elec/Plmb/HVAC | 6/2/2025 | Approved | JUAN ALVARADO |
| Wood Frame | 6/2/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 6/9/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 6/9/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 6/9/2025 | Approved | JUAN ALVARADO |
| Insulation | 6/12/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 6/20/2025 | Approved | JUAN ALVARADO |
| Final | 9/8/2025 | Corrections Issued | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 9/8/2025 | Approved | ARUTYUN MADATYAN |
| Final | 9/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 9/18/2025 | Approved | JUAN ALVARADO |
| Final | 9/18/2025 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 9/18/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 9/18/2025 | Approved | JUAN ALVARADO |
| Service/Power Release | 9/18/2025 | Approved | JUAN ALVARADO |