1509 W SCOTT AVE 90026
Certificate Information: 1509 W SCOTT AVE 90026
- Application / Permit
- 25016-10000-00177
- Plan Check / Job No.
- B25LA00149
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) detached Garage to an ADU. Work per engineer. Checked per GCS 66323(a)(2) (Previously 65852.2(e)(1)(A))
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- Current Status
- CofO Corrected on 3/16/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2025 | EDWIN MARTINEZ |
| Corrections Issued | 1/10/2025 | EDWIN MARTINEZ |
| Applicant returned to address corrections | 1/28/2025 | JOHN MESIAS |
| Plan Check Approved | 2/2/2025 | JOHN MESIAS |
| Plan Check Approved | 2/5/2025 | INTERNET PERMIT |
| Issued | 2/6/2025 | APPLICANT |
| CofO in Progress | 7/3/2025 | HAMIK HARTOUNIAN |
| CofO Issued-Status Void | 7/5/2025 | DEROLD HAUFF |
| Permit Finaled-Status Void | 7/5/2025 | DEROLD HAUFF |
| Re-Activate Permit | 3/16/2026 | DEROLD HAUFF |
| Permit Finaled | 3/16/2026 | DEROLD HAUFF |
| CofO Corrected | 3/16/2026 | DEROLD HAUFF |
| Permit Finaled | 3/16/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/11/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2025 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 1/13/2025 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/14/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 3/10/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/11/2025 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/11/2025 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 4/3/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 4/7/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 4/7/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 4/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 4/10/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 4/14/2025 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 4/14/2025 | Partial Approval | ALEX COLIN |
| Green Building Rough | 4/16/2025 | Approved | WILLIAM SIERRA |
| Wood Frame | 4/16/2025 | Approved | WILLIAM SIERRA |
| Insulation | 4/21/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/2/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/9/2025 | Approved | ANTHONY RAMOS |
| Final | 6/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/25/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/25/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 6/30/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/30/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 7/2/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |