1509 W SCOTT AVE 90026

Certificate Information: 1509 W SCOTT AVE 90026

Application / Permit
25016-10000-00177
Plan Check / Job No.
B25LA00149
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) detached Garage to an ADU. Work per engineer. Checked per GCS 66323(a)(2) (Previously 65852.2(e)(1)(A))
Permit Issued
Issued on 2/6/2025
Issuing Office
Current Status
CofO Corrected on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2025 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 EDWIN MARTINEZ
Corrections Issued 1/10/2025 EDWIN MARTINEZ
Applicant returned to address corrections 1/28/2025 JOHN MESIAS
Plan Check Approved 2/2/2025 JOHN MESIAS
Plan Check Approved 2/5/2025 INTERNET PERMIT
Issued 2/6/2025 APPLICANT
CofO in Progress 7/3/2025 HAMIK HARTOUNIAN
CofO Issued-Status Void 7/5/2025 DEROLD HAUFF
Permit Finaled-Status Void 7/5/2025 DEROLD HAUFF
Re-Activate Permit 3/16/2026 DEROLD HAUFF
Permit Finaled 3/16/2026 DEROLD HAUFF
CofO Corrected 3/16/2026 DEROLD HAUFF
Permit Finaled 3/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/11/2025 CARLOS AGUILERA
Sewer availability Cleared 1/11/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/13/2025 CARLOS AGUILERA
Grading Pre-Inspection Cleared 1/13/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2025 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 3/10/2025 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/11/2025 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/11/2025 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 4/3/2025 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 4/7/2025 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 4/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Approved WILLIAM SIERRA
Green Building Rough 4/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 4/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 4/14/2025 Not Ready for Inspection ALEX COLIN
Interior/Exterior Lathing 4/14/2025 Partial Approval ALEX COLIN
Green Building Rough 4/16/2025 Approved WILLIAM SIERRA
Wood Frame 4/16/2025 Approved WILLIAM SIERRA
Insulation 4/21/2025 Approved HAMIK HARTOUNIAN
Drywall Nailing 5/2/2025 Approved ALEX COLIN
Interior/Exterior Lathing 5/9/2025 Approved ANTHONY RAMOS
Final 6/25/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/25/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 6/25/2025 Approved HAMIK HARTOUNIAN
Final 6/30/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/30/2025 Approved HAMIK HARTOUNIAN
Final 7/2/2025 OK to Issue CofO HAMIK HARTOUNIAN