158 S CITRUS AVE 90036
Certificate Information: 158 S CITRUS AVE 90036
- Application / Permit
- 25016-10000-00103
- Plan Check / Job No.
- B24LA35998
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-CAR GARAGE TO BECOME AN ACCESSORY DWELLIG UNIT WITH NEW ATTACHED TRELLIS ADU PER STATE LAW GC 66323(a)(1)
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Current Status
- Issued on 7/11/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | JAD BASMA |
| Corrections Issued | 1/3/2025 | JAD BASMA |
| Quality Review Completed | 1/6/2025 | GARO TELMI |
| Applicant returned to address corrections | 1/29/2025 | JAD BASMA |
| Applicant returned to address corrections | 1/30/2025 | JAD BASMA |
| Plan Check Approved | 7/9/2025 | JAD BASMA |
| Issued | 7/11/2025 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 1/7/2025 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 1/8/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/8/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2025 | DAVID LOPEZ |
| HPOZ | Cleared | 1/14/2025 | RAFAEL FONTES |
| ZI | Cleared | 1/14/2025 | RAFAEL FONTES |
| Address approval | Cleared | 1/31/2025 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 4/2/2025 | PATRICK PEREZ |
| Construction near power lines | Cleared | 6/16/2025 | RIDWAN HARDY |
Contact Information
| Contractor | M & D Development & Construction Inc; Lic. No.: 736716-B | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2025 | Corrections Issued | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/16/2025 | Approved | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 12/1/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/2/2025 | Approved | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Rough | 2/13/2026 | Approved | ENRIQUE MIRELES |
| Wood Frame | 2/13/2026 | Corrections Issued | ENRIQUE MIRELES |
| Insulation | 3/18/2026 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 3/20/2026 | Not Ready for Inspection | JOSH MEISTER |
| Drywall Nailing | 3/25/2026 | Approved | ALEX COLIN |