4516 N BRUNSWICK AVE 90039
Certificate Information: 4516 N BRUNSWICK AVE 90039
- Application / Permit
- 25014-70000-05057
- Plan Check / Job No.
- B25SL01306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage with addition into ADU per state law.
- Permit Issued
- Issued on 2/12/2026
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 2/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2025 | RICARDO RAMIREZ |
| Corrections Issued | 11/15/2025 | RICARDO RAMIREZ |
| Building Plans Picked Up | 11/20/2025 | APPLICANT |
| Issued | 2/12/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 12/10/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 12/12/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 2/9/2026 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/24/2026 | Conditional Approval | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/25/2026 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 3/25/2026 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Rough | 4/6/2026 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Pre-Inspection | 4/6/2026 | Partial Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 4/21/2026 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 4/21/2026 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/21/2026 | Corrections Issued | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 4/30/2026 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 4/30/2026 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 4/30/2026 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/30/2026 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 5/5/2026 | Approved | NICHOLAS LOPEZ |
| Insulation | 5/5/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 5/7/2026 | Approved | ALEX COLIN |