8981 W FOOTHILL BLVD 91040
Certificate Information: 8981 W FOOTHILL BLVD 91040
- Application / Permit
- 25014-70000-03099
- Plan Check / Job No.
- B25SL00724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two story addition to existing single story single family dwelling with roof deck *Fire sprinklers NFPA 13D req'd thru out*
- Permit Issued
- Issued on 11/4/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2025 | JOSEPH RAFOLS |
| Corrections Issued | 7/15/2025 | JOSEPH RAFOLS |
| Quality Review Completed | 7/17/2025 | KEN GILL |
| Building Plans Picked Up | 7/22/2025 | APPLICANT |
| Plan Check Approved | 11/4/2025 | JOSEPH RAFOLS |
| Issued | 11/4/2025 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/31/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 10/6/2025 | SAFA JAVANMARDI |
| GPI Written Notices | Cleared | 11/4/2025 | JOSEPH RAFOLS |
| Grading Pre-Inspection | Cleared | 11/4/2025 | GERMAN RODRIGUEZ MENDOZA |
Contact Information
| Contractor | Family Group Construction The; Lic. No.: 1094706-B | 16332 HUNSAKER AVE PARAMOUNT, CA 90723 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/6/2025 | Partial Approval | JACK KARGODORIAN |
| Sewer | 11/6/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 11/13/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/13/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 12/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Gas Test | 12/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 12/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 12/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 1/6/2026 | Conditional Approval | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 1/27/2026 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/13/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 2/13/2026 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 3/13/2026 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 3/13/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 3/17/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Shower Pan | 3/17/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 3/19/2026 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/19/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/20/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 3/20/2026 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Shower Pan | 3/20/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 3/24/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 3/24/2026 | Approved | NICHOLAS TROWBRIDGE |