8981 W FOOTHILL BLVD 91040

Certificate Information: 8981 W FOOTHILL BLVD 91040

Application / Permit
25014-70000-03099
Plan Check / Job No.
B25SL00724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Two story addition to existing single story single family dwelling with roof deck *Fire sprinklers NFPA 13D req'd thru out*
Permit Issued
Issued on 11/4/2025
Issuing Office
Metro
Current Status
Issued on 11/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/8/2025 APPLICANT
Assigned to Plan Check Engineer 7/10/2025 JOSEPH RAFOLS
Corrections Issued 7/15/2025 JOSEPH RAFOLS
Quality Review Completed 7/17/2025 KEN GILL
Building Plans Picked Up 7/22/2025 APPLICANT
Plan Check Approved 11/4/2025 JOSEPH RAFOLS
Issued 11/4/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 7/31/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/6/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 10/6/2025 SAFA JAVANMARDI
GPI Written Notices Cleared 11/4/2025 JOSEPH RAFOLS
Grading Pre-Inspection Cleared 11/4/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Family Group Construction The; Lic. No.: 1094706-B 16332 HUNSAKER AVE      PARAMOUNT, CA 90723
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/6/2025 Partial Approval JACK KARGODORIAN
Sewer 11/6/2025 Not Ready for Inspection JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 11/13/2025 Approved DAVID ANDERSON
Footing/Foundation/Slab 11/13/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Corrections Issued NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 12/23/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Gas Test 12/23/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 12/23/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Rough-Elec/Plmb/HVAC 12/23/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 1/6/2026 Conditional Approval NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 1/27/2026 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 2/13/2026 Corrections Issued MATTHEW NELSON
Green Building Rough 2/13/2026 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 3/13/2026 Approved NICHOLAS TROWBRIDGE
Green Building Rough 3/13/2026 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 3/13/2026 Approved NICHOLAS TROWBRIDGE
Insulation 3/17/2026 Corrections Issued NICHOLAS TROWBRIDGE
Shower Pan 3/17/2026 Approved NICHOLAS TROWBRIDGE
Insulation 3/19/2026 Approved MICHEL ABAJAN
Shower Pan 3/19/2026 Approved MICHEL ABAJAN
Drywall Nailing 3/20/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 3/20/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE
Shower Pan 3/20/2026 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 3/24/2026 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 3/24/2026 Approved NICHOLAS TROWBRIDGE