- Work Description
- Alteration to single family dwelling to convert portion of dwelling into JADU (390sf). Convert attached garage will small addition to ADU (454sf) per state law. Minor remodel of existing sfd at kitchen and bathroom areas. Create additional third bedroom to existing two bedroom dwelling.
- Permit Issued
- Issued on 7/1/2025
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2025 | RICARDO RAMIREZ |
| Corrections Issued | 6/3/2025 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/24/2025 | LUKE GONZALES |
| Issued | 7/1/2025 | APPLICANT |
| CofO in Progress | 4/7/2026 | JOSEPH MCGARRY |
| Permit Finaled | 4/7/2026 | ANSON MAGLASANG |
| CofO Issued | 4/7/2026 | ANSON MAGLASANG |
| Permit Finaled | 4/7/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/6/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/24/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Baumeister Construction; Lic. No.: 1107111-B | 1379 W PARK WESTERN DR STE 608 SAN PEDRO, CA 90732 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/17/2025 | Corrections Issued | BEN MOLSTAD |
| METHANE-Barrier | 7/17/2025 | Not Ready for Inspection | BEN MOLSTAD |
| METHANE-Subgrade | 7/17/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 9/15/2025 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 9/15/2025 | No Access for Inspection | EUGENE CASSIDY |
| METHANE-Subgrade | 9/15/2025 | No Access for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/10/2025 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 10/10/2025 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 10/10/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/10/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/15/2025 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 10/16/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/4/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/12/2025 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 11/12/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Conditional Approval | JOSEPH MCGARRY |
| HVAC-Rough | 11/12/2025 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/12/2025 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 11/12/2025 | Approved | JOSEPH MCGARRY |
| Shower Pan | 11/12/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/26/2025 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 11/26/2025 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2025 | Approved | JOSEPH MCGARRY |
| Insulation | 11/26/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/26/2025 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 12/3/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 12/3/2025 | Approved | EUGENE CASSIDY |
| Insulation | 12/3/2025 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 12/3/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/3/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/5/2025 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 12/15/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/15/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/16/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/16/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/23/2026 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/20/2026 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/20/2026 | Approved | JOSEPH MCGARRY |
| Green Building Final | 3/20/2026 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 3/20/2026 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/25/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 3/25/2026 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 3/25/2026 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV Not Ready | BEN MOLSTAD |
| ELECTRICAL-Final | 3/27/2026 | Approved | JOSEPH MCGARRY |
| Final | 3/27/2026 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Approved | JOSEPH MCGARRY |