6652-6654 N BELMAR AVE 91335

Certificate Information: 6652-6654 N BELMAR AVE 91335

Application / Permit
25014-70000-02330
Plan Check / Job No.
B25SL00548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and conversion of existing attached garage into an ADU per LAMC 12.22 A.33 (c) & (e).
Permit Issued
Issued on 6/10/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2025 APPLICANT
Assigned to Plan Check Engineer 5/28/2025 RICARDO RAMIREZ
Corrections Issued 5/28/2025 RICARDO RAMIREZ
Issued 6/10/2025 APPLICANT
CofO in Progress 5/7/2026 JUAN ALVARADO
Permit Finaled 5/21/2026 JOHN JANSON
Permit Finaled 5/21/2026 JOHN JANSON
CofO Issued 5/21/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/2/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/2/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/3/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/3/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/2/2025 Partial Approval JUAN ALVARADO
Underground Mechanical 7/2/2025 Not Ready for Inspection JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 7/16/2025 Not Ready for Inspection JUAN ALVARADO
Footing/Foundation/Slab 7/16/2025 Not Ready for Inspection JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 7/22/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 7/22/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 9/9/2025 Partial Approval JUAN ALVARADO
ELECTRICAL-Rough 9/9/2025 Corrections Issued JUAN ALVARADO
Green Building Rough 9/9/2025 Not Ready for Inspection JUAN ALVARADO
Rough-Elec/Plmb/HVAC 9/9/2025 Approved JUAN ALVARADO
Insulation 9/24/2025 Partial Approval JON MCHUGH
Interior/Exterior Lathing 9/24/2025 Corrections Issued JON MCHUGH
Insulation 9/29/2025 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/29/2025 Partial Approval KRISTEN CAUSEY
Drywall Nailing 10/9/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 10/9/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 10/28/2025 Approved JUAN ALVARADO
ELECTRICAL-Rough 10/28/2025 Approved JUAN ALVARADO
Green Building Rough 10/28/2025 Approved JUAN ALVARADO
Pre-Inspection 10/28/2025 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 12/11/2025 Partial Approval ARUTYUN MADATYAN
Final 3/24/2026 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 3/24/2026 Approved JUAN ALVARADO
Green Building Final 3/24/2026 Not Ready for Inspection JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Not Ready JUAN ALVARADO
Smoke Detectors 3/24/2026 Approved JUAN ALVARADO
Final 5/1/2026 Corrections Issued JUAN ALVARADO
Green Building Final 5/1/2026 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Approved JUAN ALVARADO
ELECTRICAL-Final 5/6/2026 Approved JUAN ALVARADO
Final 5/6/2026 OK to Issue CofO JUAN ALVARADO
HVAC-Final 5/6/2026 Approved JUAN ALVARADO
PLUMBING-Final 5/6/2026 Approved JUAN ALVARADO