648 E 76TH ST 90001
Certificate Information: 648 E 76TH ST 90001
- Application / Permit
- 25014-70000-01398
- Plan Check / Job No.
- B25SL00287
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One story addition to rear of dwelling to add family room, bedroom and bathroom. Remodel existing dwelling to relocate kitchen and create an additional bedroom.
- Permit Issued
- Issued on 4/4/2025
- Issuing Office
- Metro
- Current Status
- Issued on 4/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2025 | RICARDO RAMIREZ |
| Corrections Issued | 4/1/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 4/3/2025 | RICARDO RAMIREZ |
| Issued | 4/4/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2025 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 4/1/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 4/1/2025 | COLIN LOREDO |
| Community Plan Implem. Overlay | Cleared | 4/3/2025 | ANACANY HURTADO |
| ZI | Cleared | 4/3/2025 | ANACANY HURTADO |
Contact Information
| Contractor | Cornerstone Builders And Restoration Inc; Lic. No.: 950235-B | 1814 E ALONDRA BLVD COMPTON, CA 90221 |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: C64738 | 16111 PRAIRIE AVE APT. 117 LAWNDALE, CA 90260 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/1/2025 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 5/19/2025 | Corrections Issued | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Wood Frame | 6/11/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 7/21/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | JOHN QUINTANILLA |
| Insulation | 7/23/2025 | Partial Approval | JOHN QUINTANILLA |
| PLUMBING-Rough | 7/23/2025 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 8/14/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 8/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 8/25/2025 | Approved | LUIS CASTRO |
| Gas Test | 8/25/2025 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 8/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 8/25/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 8/25/2025 | Approved | LUIS CASTRO |
| Shower Pan | 8/25/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/27/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 8/27/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 8/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 10/30/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 10/30/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 10/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Final | 11/3/2025 | Corrections Issued | BARRY HACHE |
| Final | 11/3/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 11/3/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 11/5/2025 | Partial Inspection | JOHN QUINTANILLA |
| Final | 11/5/2025 | Partial Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 11/5/2025 | Partial Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 11/12/2025 | Approved | JOHN QUINTANILLA |
| Final | 11/12/2025 | Conditional Approval | JOHN QUINTANILLA |
| Smoke Detectors | 11/12/2025 | Approved | JOHN QUINTANILLA |