1512 E 32ND ST 90011
Certificate Information: 1512 E 32ND ST 90011
- Application / Permit
- 25014-70000-01370
- Plan Check / Job No.
- B25SL00284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to existing single family dwelling and replace roof. Reframe portion of the roof. All work per engineering "COMPLY WITH DEPARTMENT ORDER effective date 10/04/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" 1 of 2
- Permit Issued
- Issued on 12/8/2025
- Issuing Office
- Valley
- Current Status
- Issued on 12/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2025 | RICARDO RAMIREZ |
| Corrections Issued | 4/3/2025 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 8/21/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 12/8/2025 | SEWADA ZADOORIAN MILAGARDI |
| Issued | 12/8/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/11/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/11/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | ADRIAN SANCHEZ |
| Historic Resource Verification | Cleared | 6/16/2025 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 6/30/2025 | YASMINE BASHIRI |
| ZI | Cleared | 6/30/2025 | YASMINE BASHIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 1038 FLANDERS RD LA CANADA-FLNTRDG, CA 91011 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2026 | Partial Inspection | DANIEL GONZALEZ |
| Deputy Drilled-In Anchors | 2/13/2026 | No Access for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 2/18/2026 | Partial Approval | DANIEL GONZALEZ |
| Rough-Elec/Plmb/HVAC | 2/18/2026 | Partial Approval | DANIEL GONZALEZ |
| Shower Pan | 2/18/2026 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 3/23/2026 | Partial Approval | DANIEL GONZALEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Partial Approval | DANIEL GONZALEZ |