2625 S AVERILL AVE 90731
Certificate Information: 2625 S AVERILL AVE 90731
- Application / Permit
- 25014-40000-00196
- Plan Check / Job No.
- B25SP00161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 20'-4" X 23' MASTER BEDROOM/BATHROOM/W.I.C. AT REAR OF (E) SFD.
- Permit Issued
- Issued on 8/19/2025
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 2/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/21/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/30/2025 | APPLICANT |
| Applicant returned to address corrections | 3/18/2025 | LAWRENCE QUIRANTE |
| Plan Check Approved | 8/5/2025 | LAWRENCE QUIRANTE |
| Issued | 8/19/2025 | APPLICANT |
| CofO in Progress | 2/24/2026 | JOSEPH MCGARRY |
| Permit Finaled | 2/25/2026 | ANSON MAGLASANG |
| CofO Issued | 2/25/2026 | ANSON MAGLASANG |
| Permit Finaled | 2/25/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/3/2025 | MATTHEW JENKINS |
| Roof/Waste drainage to street | Cleared | 3/27/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2025 | XOCHITL ARQUIETA |
| Coastal Zone | Cleared | 7/31/2025 | JACQUELINE TORRES |
Contact Information
| Architect | Flood,, Joyce G; Lic. No.: C26847 | 505 N SEPULVEDA BLVD SUITE 4 MANHATTAN BEACH, CA 90266 |
| Contractor | M F R Construction; Lic. No.: 544888-B | 2503 CARNEGIE LANE #1 REDONDO BEACH, CA 90278 |
| Engineer | Guirguis,, Diaa; Lic. No.: C40731 | 1320 19TH ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2025 | Approved | BEN MOLSTAD |
| Footing/Foundation/Slab | 10/6/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/23/2025 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 10/23/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/23/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 10/24/2025 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 10/30/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/24/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 11/24/2025 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 11/24/2025 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 11/24/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/24/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 12/10/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/10/2025 | Approved | JOSEPH MCGARRY |
| Shower Pan | 12/10/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/19/2026 | Approved | JOSEPH MCGARRY |
| Final | 2/19/2026 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 2/19/2026 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 2/19/2026 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/19/2026 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/19/2026 | Approved | JOSEPH MCGARRY |