7546 N DENSMORE AVE 91406

Certificate Information: 7546 N DENSMORE AVE 91406

Application / Permit
25014-30000-05336
Plan Check / Job No.
B25WL09300
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story attached ADU per LAMC12.22A.33(c) and(e)
Permit Issued
Issued on 2/2/2026
Issuing Office
West Los Angeles
Current Status
Issued on 2/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/4/2025 APPLICANT
Assigned to Plan Check Engineer 12/9/2025 RICHARD GARCIA
Corrections Issued 12/10/2025 RICHARD GARCIA
Applicant returned to address corrections 1/26/2026 KAVIAN REFAHI
Plan Check Approved 2/2/2026 JOHNPAUL ISIP
Issued 2/2/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/12/2026 CARLOS AGUILERA
Address approval Cleared 1/21/2026 JESUS CISNEROS
Miscellaneous Cleared 1/21/2026 JESUS CISNEROS
Sewer availability Cleared 1/22/2026 JESUS CISNEROS
Roof/Waste drainage to street Cleared 1/28/2026 JESUS CISNEROS

Contact Information

Contractor Owner-Builder       ,
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/13/2026 Partial Approval GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 2/23/2026 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 2/24/2026 Conditional Approval KIRK SANDERS
Wood Frame 3/16/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/6/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 4/15/2026 Corrections Issued MICHAEL CORTEZ
Gas Test 4/15/2026 Partial Approval MICHAEL CORTEZ
HVAC-Rough 4/15/2026 Corrections Issued MICHAEL CORTEZ
ELECTRICAL-Rough 4/21/2026 Corrections Issued VINCENT HANLEY
HVAC-Rough 4/21/2026 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 4/21/2026 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/21/2026 Corrections Issued VINCENT HANLEY
Shower Pan 4/21/2026 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/27/2026 Approved MICHAEL CORTEZ
HVAC-Rough 4/27/2026 Not Ready for Inspection MICHAEL CORTEZ
PLUMBING-Rough 4/27/2026 Not Ready for Inspection MICHAEL CORTEZ
BUILDING-Rough-Frame 4/30/2026 Partial Approval JAVIER RAMOS JR
HVAC-Rough 4/30/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/30/2026 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/30/2026 Approved JAVIER RAMOS JR
Insulation 5/6/2026 Approved MICHEL ABAJAN