5335 S 8TH AVE 90043
Certificate Information: 5335 S 8TH AVE 90043
- Application / Permit
- 25014-30000-04777
- Plan Check / Job No.
- B25WL08479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition to rear side of (e) single story SFD and remodel the house
- Permit Issued
- Issued on 2/9/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2025 | REZA HAGHIGHAT |
| Corrections Issued | 10/31/2025 | REZA HAGHIGHAT |
| Building Plans Picked Up | 11/6/2025 | APPLICANT |
| Plan Check Approved | 2/4/2026 | AMY GUEVARRA |
| Issued | 2/9/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 2/2/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 2/2/2026 | MICHAEL BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Deihimi,, Amir; Lic. No.: C78194 | 201 E SANDPOINTE AVE STE 400 SANTA ANA, CA 92707 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2026 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 3/27/2026 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2026 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/7/2026 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 5/7/2026 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 5/7/2026 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 5/7/2026 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 5/7/2026 | Approved | LUIS CASTRO |
| Wood Frame | 5/7/2026 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 5/15/2026 | Approved | LUIS CASTRO |
| Green Building Rough | 5/15/2026 | Approved | LUIS CASTRO |
| Insulation | 5/15/2026 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 5/15/2026 | Partial Approval | LUIS CASTRO |
| Shower Pan | 5/15/2026 | Approved | LUIS CASTRO |
| Drywall Nailing | 5/27/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/27/2026 | Approved | ALEX COLIN |