3565 S GREENWOOD AVE 90066

Certificate Information: 3565 S GREENWOOD AVE 90066

Application / Permit
25014-30000-04741
Plan Check / Job No.
B25WL08435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel, ground floor and a new 2nd floor addition with fully sprinkler bulding to (E) 1--story SFD
Permit Issued
Issued on 1/27/2026
Issuing Office
West Los Angeles
Current Status
Issued on 1/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/24/2025 APPLICANT
Assigned to Plan Check Engineer 10/30/2025 ZENA HADDIS
Assigned to Zoning Architect 10/30/2025 MELISSA QUINONES
Corrections Issued 11/21/2025 ZENA HADDIS
Quality Review Completed 11/21/2025 CHIHARU SUZUKI
Building Plans Picked Up 11/24/2025 APPLICANT
Plan Check Approved 1/27/2026 ZENA HADDIS
Issued 1/27/2026 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/13/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 11/17/2025 JESUS CISNEROS
Sewer availability Cleared 11/17/2025 JESUS CISNEROS
Specific Plan Cleared 11/20/2025 RICHARD WOO
Miscellaneous Cleared 12/10/2025 DAVID URITA
Miscellaneous Cleared 12/10/2025 DAVID URITA
Miscellaneous Cleared 12/10/2025 DAVID URITA
Zoning Plan Check Cleared 1/20/2026 MELISSA QUINONES
Grading Pre-Inspection Cleared 1/27/2026 ZENA HADDIS

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2026 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 3/16/2026 Partial Approval MICHAEL ALLEN
Sewer 3/16/2026 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 3/20/2026 Approved DAKOTA LOW
Footing/Foundation/Slab 3/20/2026 Conditional Approval DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 4/14/2026 Partial Approval DAKOTA LOW
Deputy Wood Construction 5/21/2026 Conditional Approval DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 5/26/2026 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 6/2/2026 Approved DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 6/9/2026 Corrections Issued MORRIS JACKSON
HVAC-Rough 6/9/2026 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 6/12/2026 Approved DAKOTA LOW
BUILDING-Rough-Frame 6/18/2026 Not Ready for Inspection MORRIS JACKSON
Green Building Rough 6/18/2026 Not Ready for Inspection MORRIS JACKSON
Wood Frame 6/18/2026 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 6/26/2026 Corrections Issued DAKOTA LOW
Green Building Rough 6/26/2026 Approved DAKOTA LOW
HVAC-Rough 6/26/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 6/26/2026 Partial Approval DAKOTA LOW
BUILDING-Rough-Frame 7/1/2026 Approved DAKOTA LOW
Insulation 7/8/2026 Approved DAKOTA LOW
Shower Pan 7/10/2026 Approved DAKOTA LOW
Drywall Nailing 7/15/2026 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/17/2026 Approved DAKOTA LOW