3565 S GREENWOOD AVE 90066
Certificate Information: 3565 S GREENWOOD AVE 90066
- Application / Permit
- 25014-30000-04741
- Plan Check / Job No.
- B25WL08435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel, ground floor and a new 2nd floor addition with fully sprinkler bulding to (E) 1--story SFD
- Permit Issued
- Issued on 1/27/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2025 | ZENA HADDIS |
| Assigned to Zoning Architect | 10/30/2025 | MELISSA QUINONES |
| Corrections Issued | 11/21/2025 | ZENA HADDIS |
| Quality Review Completed | 11/21/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/24/2025 | APPLICANT |
| Plan Check Approved | 1/27/2026 | ZENA HADDIS |
| Issued | 1/27/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/13/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 11/17/2025 | JESUS CISNEROS |
| Specific Plan | Cleared | 11/20/2025 | RICHARD WOO |
| Miscellaneous | Cleared | 12/10/2025 | DAVID URITA |
| Miscellaneous | Cleared | 12/10/2025 | DAVID URITA |
| Miscellaneous | Cleared | 12/10/2025 | DAVID URITA |
| Zoning Plan Check | Cleared | 1/20/2026 | MELISSA QUINONES |
| Grading Pre-Inspection | Cleared | 1/27/2026 | ZENA HADDIS |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | MICHAEL ALLEN |
| Sewer | 3/16/2026 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 3/20/2026 | Approved | DAKOTA LOW |
| Footing/Foundation/Slab | 3/20/2026 | Conditional Approval | DAKOTA LOW |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2026 | Partial Approval | DAKOTA LOW |
| Deputy Wood Construction | 5/21/2026 | Conditional Approval | DAKOTA LOW |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/26/2026 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/2/2026 | Approved | DAKOTA LOW |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2026 | Corrections Issued | MORRIS JACKSON |
| HVAC-Rough | 6/9/2026 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 6/12/2026 | Approved | DAKOTA LOW |
| BUILDING-Rough-Frame | 6/18/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Green Building Rough | 6/18/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 6/18/2026 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/26/2026 | Corrections Issued | DAKOTA LOW |
| Green Building Rough | 6/26/2026 | Approved | DAKOTA LOW |
| HVAC-Rough | 6/26/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 6/26/2026 | Partial Approval | DAKOTA LOW |
| BUILDING-Rough-Frame | 7/1/2026 | Approved | DAKOTA LOW |
| Insulation | 7/8/2026 | Approved | DAKOTA LOW |
| Shower Pan | 7/10/2026 | Approved | DAKOTA LOW |
| Drywall Nailing | 7/15/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/17/2026 | Approved | DAKOTA LOW |