11404 W BIONA DR 90066
Certificate Information: 11404 W BIONA DR 90066
- Application / Permit
- 25014-30000-04661
- Plan Check / Job No.
- B25WL08264
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) SFD and interior remodel
- Permit Issued
- Issued on 11/24/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2025 | RICHARD GARCIA |
| Corrections Issued | 10/29/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 11/3/2025 | APPLICANT |
| Applicant returned to address corrections | 11/19/2025 | DAVID CASTILLO |
| Plan Check Approved | 11/19/2025 | BEHROUZ KHOKHAR |
| Issued | 11/24/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 11/4/2025 | XOCHITL ARQUIETA |
| Specific Plan | Cleared | 11/12/2025 | HAMID GHAEMMAGHAMI |
| Grading Pre-Inspection | Cleared | 11/17/2025 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 11/18/2025 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Airola,, Travis Tone; Lic. No.: C88832 | 414 SUPERIOR WAY DISCOVERY BAY, CA 94505 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/9/2026 |
| BUILDING-Rough-Frame | 6/9/2026 |
| Smoke Detectors | 6/9/2026 |
| SGSOV-Seismic Gas S/O Valve | 6/9/2026 |
| Green Building Final | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2025 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 12/1/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 12/3/2025 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/8/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 12/8/2025 | Approved | MICHAEL ALLEN |
| Sewer | 12/8/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Underground Mechanical | 12/8/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Deputy Reinf. Concrete | 12/9/2025 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2026 | Not Ready for Inspection | ANDREW NAVE |
| Wood Frame | 2/23/2026 | Corrections Issued | ANDREW NAVE |
| Deputy Wood Construction | 2/24/2026 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 2/25/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/27/2026 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 2/27/2026 | Partial Approval | MICHAEL ALLEN |
| Wood Frame | 2/27/2026 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 3/12/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 3/12/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/16/2026 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/16/2026 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 3/16/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 3/16/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/20/2026 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 3/20/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/20/2026 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 3/25/2026 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/25/2026 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 3/31/2026 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/31/2026 | Partial Approval | ANDREW NAVE |
| Shower Pan | 3/31/2026 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 4/1/2026 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 4/27/2026 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 4/27/2026 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/1/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 5/1/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 5/11/2026 | Approved | EUGENE CASSIDY |
| HVAC-Final | 5/11/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 5/15/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 5/20/2026 | Approved | KIRK SANDERS |