7135 W 91ST ST 90045
Certificate Information: 7135 W 91ST ST 90045
- Application / Permit
- 25014-30000-04650
- Plan Check / Job No.
- B25WL08249
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to an (e) sfd. Addition to include expansion of bedroom/bath.
- Permit Issued
- Issued on 12/4/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 12/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2025 | RICHARD GARCIA |
| Corrections Issued | 10/24/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 10/31/2025 | APPLICANT |
| Plan Check Approved | 12/4/2025 | RICHARD GARCIA |
| Issued | 12/4/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/6/2025 | JEFF LOREDO |
| Sewer availability | Cleared | 11/6/2025 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2025 | ROSE STEIN-WENDT |
| Specific Plan | Cleared | 11/26/2025 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2026 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2026 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2026 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/20/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 3/20/2026 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 3/27/2026 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 3/27/2026 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 4/3/2026 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/3/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/10/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/10/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/10/2026 | Partial Approval | MICHAEL ALLEN |
| Shower Pan | 4/10/2026 | Approved | MICHAEL ALLEN |
| Insulation | 4/15/2026 | Approved | JESUS PINEDA |
| Drywall Nailing | 4/23/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/23/2026 | Approved | JESUS PINEDA |