3338-3340 S MEIER ST 90066

Certificate Information: 3338-3340 S MEIER ST 90066

Application / Permit
25014-30000-03962
Plan Check / Job No.
B25WL07114
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Major remodel addition w/new 2nd floor & new attached ADU PER 12.22 a.33 (c) and (e) to existing 1 story SFD w/attached Garage. NFPD 13D Sprinkler
Permit Issued
Issued on 10/17/2025
Issuing Office
West Los Angeles
Current Status
Issued on 10/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/2/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 ZENA HADDIS
Assigned to Zoning Architect 9/4/2025 NICOLE SALEEBA
Corrections Issued 9/15/2025 ZENA HADDIS
Quality Review Completed 9/23/2025 CHIHARU SUZUKI
Building Plans Picked Up 9/24/2025 APPLICANT
Plan Check Approved 10/15/2025 ZENA HADDIS
No Progress 10/17/2025 IRMA BARRAZA
Plan Check Approved 10/17/2025 ZENA HADDIS
Issued 10/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/24/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/24/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 9/24/2025 WALLIE JONG
Sewer availability Cleared 9/24/2025 WALLIE JONG
Trees in Parkway Cleared 9/24/2025 MIGUEL ORNELAS
Specific Plan Cleared 9/25/2025 EDER ROMERO
CPC Cleared 9/30/2025 DALIA MOKAYED
CPC Cleared 9/30/2025 DALIA MOKAYED
Zoning Plan Check Cleared 10/10/2025 NICOLE SALEEBA
Grading Pre-Inspection Cleared 10/15/2025 ZENA HADDIS

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Vip Construction 1 Inc; Lic. No.: 1097925-B 11038 BENWELL DRIVE APT D      LYNWOOD, CA 90262
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Tsao,, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2025 Partial Approval KENNETH NAGLE
Sewer 12/1/2025 Approved KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 12/5/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 12/5/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 12/9/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval WILBER ROSALES
PLUMBING-Rough 1/28/2026 Partial Approval MICHAEL ALLEN
Underground Mechanical 1/28/2026 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Partial Approval ANTHONY EGSON
HVAC-Rough 2/5/2026 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 2/5/2026 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 2/9/2026 Approved ANTHONY EGSON
PLUMBING-Rough 2/9/2026 Approved ANTHONY EGSON
ELECTRICAL-Rough 2/12/2026 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 3/19/2026 Not Ready for Inspection DAKOTA LOW
ELECTRICAL-Rough 3/19/2026 Approved DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Approved DAKOTA LOW
Green Building Rough 3/19/2026 Corrections Issued DAKOTA LOW
Interior/Exterior Lathing 3/19/2026 Partial Approval DAKOTA LOW
BUILDING-Rough-Frame 3/26/2026 Approved DAKOTA LOW
Green Building Rough 3/26/2026 Approved DAKOTA LOW
Verify Sprinkler Sign Off 3/26/2026 Approved DAKOTA LOW
Insulation 4/6/2026 Corrections Issued JESUS PINEDA
Insulation 4/9/2026 Approved RYAN SALAZAR
Drywall Nailing 4/20/2026 Approved DAKOTA LOW
Shower Pan 4/20/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 4/23/2026 Approved DAKOTA LOW