11411 W CHARNOCK ROAD 90066
Certificate Information: 11411 W CHARNOCK ROAD 90066
- Application / Permit
- 25014-30000-03777
- Plan Check / Job No.
- B25WL06838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to rear of SFD, enclose (E) covered entry porch and add (N) front porch COMPLY WITH DEPARTMENT ORDER effective date 06/04/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 1048365.
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/25/2025 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 8/27/2025 | APPLICANT |
| Plan Check Approved | 11/20/2025 | AMY GUEVARRA |
| Issued | 11/25/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/5/2025 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 11/20/2025 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorier,, David Julien Miche; Lic. No.: S7064 | 950 S GRAND AVE 4TH FLOOR LOS ANGELES, CA 90015 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/15/2026 | Approved | RYAN BARNES |
| Excavation/Setback/Form/Re-Bar | 1/28/2026 | Approved | RYAN BARNES |
| Footing/Foundation/Slab | 1/28/2026 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 2/10/2026 | Partial Approval | RYAN BARNES |
| Pre-Inspection | 2/10/2026 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 3/5/2026 | Approved | RYAN BARNES |
| Green Building Rough | 3/5/2026 | Approved | RYAN BARNES |
| Wood Frame | 3/5/2026 | Conditional Approval | RYAN BARNES |
| ELECTRICAL-Rough | 3/11/2026 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 3/11/2026 | Partial Approval | RYAN BARNES |
| PLUMBING-Rough | 3/11/2026 | Approved | RYAN BARNES |
| Insulation | 3/16/2026 | Approved | RYAN BARNES |
| Drywall Nailing | 3/23/2026 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 3/23/2026 | Approved | RYAN BARNES |
| Final | 5/7/2026 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Final | 5/7/2026 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 5/7/2026 | Approved | ANDREW BEELI |
| Final | 5/27/2026 | Partial Approval | ANDREW BEELI |
| Green Building Final | 5/27/2026 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 5/27/2026 | SGSOV Approved | ANDREW BEELI |