1338 N AVENIDA DE CORTEZ 90272
Certificate Information: 1338 N AVENIDA DE CORTEZ 90272
- Application / Permit
- 25014-30000-03566
- Plan Check / Job No.
- B25WL06435
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel to (E) 2-story S.F.D. with attached garage.
- Permit Issued
- Issued on 11/3/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2025 | REZA HAGHIGHAT |
| Corrections Issued | 8/10/2025 | REZA HAGHIGHAT |
| Building Plans Picked Up | 8/12/2025 | APPLICANT |
| Applicant returned to address corrections | 9/18/2025 | CAROLEAN BASMA |
| Plan Check Approved | 9/23/2025 | ALFREDO JARA |
| Issued | 11/3/2025 | APPLICANT |
| CofO in Progress | 7/6/2026 | MICHAEL ALLEN |
| Permit Finaled | 7/7/2026 | RICHARD STEINBACH |
| CofO Issued | 7/7/2026 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/14/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 8/14/2025 | JEREMY CHOK |
| Grading Pre-Inspection | Cleared | 8/18/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2025 | JEREMY CHOK |
| Coastal Zone | Cleared | 9/10/2025 | ALEX VELA |
| Miscellaneous | Cleared | 9/10/2025 | ALEX VELA |
| Private street | Cleared | 9/10/2025 | ALEX VELA |
| ZA Case | Cleared | 9/10/2025 | ALEX VELA |
| ZA Case | Cleared | 9/10/2025 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/5/2025 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/7/2025 | Conditional Approval | BOBBY KEY |
| Underground Mechanical | 11/19/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 11/21/2025 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/13/2026 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 1/13/2026 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/13/2026 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 2/5/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 2/5/2026 | Partial Approval | DANIEL VERA |
| Rough-Elec/Plmb/HVAC | 2/5/2026 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | DANIEL VERA |
| Insulation | 2/18/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 2/23/2026 | Approved | DANIEL VERA |
| Shower Pan | 2/26/2026 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 3/16/2026 | Approved | DANIEL VERA |
| Gas Test | 6/5/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 6/17/2026 | Approved | MICHAEL ALLEN |
| Final | 6/17/2026 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 6/17/2026 | Approved | MICHAEL ALLEN |
| Green Building Final | 6/17/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 6/17/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 6/17/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 6/17/2026 | Approved | MICHAEL ALLEN |
| Final | 7/2/2026 | OK to Issue CofO | MICHAEL ALLEN |