7342-7342 1/2 N BALCOM AVE 91335

Certificate Information: 7342-7342 1/2 N BALCOM AVE 91335

Application / Permit
25014-30000-03429
Plan Check / Job No.
B25WL06221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Closet addiition at rear of sfd. JADU addition at rear of the existing SFD per GC66323(a)(1) and 66333. ***ALL WORK PER WFPP***
Permit Issued
Issued on 8/20/2025
Issuing Office
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2025 APPLICANT
Assigned to Plan Check Engineer 7/31/2025 RICHARD GARCIA
Building Plans Picked Up 8/1/2025 APPLICANT
Corrections Issued 8/2/2025 RICHARD GARCIA
Applicant returned to address corrections 8/19/2025 CAROLEAN BASMA
Plan Check Approved 8/20/2025 KAVIAN REFAHI
Issued 8/20/2025 APPLICANT
CofO in Progress 5/11/2026 JUAN ALVARADO
Permit Finaled 5/15/2026 JOHN JANSON
CofO Issued 5/15/2026 JOHN JANSON
Permit Finaled 5/15/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/9/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/9/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/11/2025 COLIN LOREDO
Sewer availability Cleared 8/11/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/7/2025 Partial Approval JUAN ALVARADO
Sewer 11/7/2025 Approved JUAN ALVARADO
Footing/Foundation/Slab 11/26/2025 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued JUAN ALVARADO
BUILDING-Rough-Frame 2/5/2026 Partial Approval JUAN ALVARADO
ELECTRICAL-Rough 2/5/2026 Approved JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Approved JUAN ALVARADO
Green Building Rough 2/5/2026 Not Ready for Inspection JUAN ALVARADO
HVAC-Rough 2/5/2026 Approved JUAN ALVARADO
PLUMBING-Rough 2/5/2026 Approved JUAN ALVARADO
Rough-Elec/Plmb/HVAC 2/5/2026 Approved JUAN ALVARADO
BUILDING-Rough-Frame 2/12/2026 Approved JUAN ALVARADO
Green Building Rough 2/12/2026 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/12/2026 Approved JUAN ALVARADO
Insulation 2/18/2026 Partial Approval GEVORK IPCHYAN
Insulation 2/20/2026 Approved JUAN ALVARADO
Shower Pan 3/27/2026 Approved JUAN ALVARADO
ELECTRICAL-Final 4/24/2026 Not Ready for Inspection JUAN ALVARADO
Final 4/24/2026 Corrections Issued JUAN ALVARADO
Green Building Final 4/24/2026 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Approved JUAN ALVARADO
Smoke Detectors 4/24/2026 Approved JUAN ALVARADO
Final 4/29/2026 Corrections Issued JUAN ALVARADO
ELECTRICAL-Final 5/8/2026 Approved JUAN ALVARADO
Final 5/8/2026 OK to Issue CofO JUAN ALVARADO
HVAC-Final 5/8/2026 Approved JUAN ALVARADO
PLUMBING-Final 5/8/2026 Approved JUAN ALVARADO
Service/Power Release 5/8/2026 Approved JUAN ALVARADO