7907 S VICKSBURG AVE 90045
Certificate Information: 7907 S VICKSBURG AVE 90045
- Application / Permit
- 25014-30000-03394
- Plan Check / Job No.
- B25WL06147
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-Story addition to rear side of (e) single story SFD and remodel
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2025 | REZA HAGHIGHAT |
| Corrections Issued | 7/28/2025 | REZA HAGHIGHAT |
| Building Plans Picked Up | 7/29/2025 | APPLICANT |
| Issued | 8/7/2025 | APPLICANT |
| CofO in Progress | 2/3/2026 | JESUS PINEDA |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
| CofO Issued | 2/5/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/5/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 8/4/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 8/6/2025 | MICHAEL BROWN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Kook & Associates Construction Inc; Lic. No.: 820560-B | 2100 SAWTELLE BLVD #306 LOS ANGELES, CA 90025 |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/22/2025 | Partial Inspection | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/26/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Approved | RUBEN RIVAS |
| Gas Test | 9/19/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 9/19/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 10/10/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 10/10/2025 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 10/10/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 10/15/2025 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/15/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 10/20/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/20/2025 | Partial Approval | JESUS PINEDA |
| Insulation | 10/23/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 10/28/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 10/28/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 10/30/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 10/30/2025 | Approved | JESUS PINEDA |
| Shower Pan | 10/30/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 12/3/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 1/12/2026 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 1/16/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 1/21/2026 | Approved | JESUS PINEDA |
| Service/Power Release | 1/21/2026 | Approved | JESUS PINEDA |
| Final | 1/27/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 1/27/2026 | Approved | JESUS PINEDA |
| HVAC-Final | 1/27/2026 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 1/27/2026 | Approved | JESUS PINEDA |
| HVAC-Final | 1/29/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Approved | JESUS PINEDA |
| Final | 2/2/2026 | OK to Issue CofO | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | JESUS PINEDA |