1621 S CORNING ST 90035

Certificate Information: 1621 S CORNING ST 90035

Application / Permit
25014-30000-03262
Plan Check / Job No.
B25WL05901
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and addition to an (E) 1-story SFD. New second story and attached garage sprinkler throughout the building.
Permit Issued
Issued on 8/29/2025
Issuing Office
West Los Angeles
Current Status
Issued on 8/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2025 APPLICANT
Assigned to Plan Check Engineer 7/24/2025 JOHN TRIANTAFYLLOS
Corrections Issued 7/30/2025 JOHN TRIANTAFYLLOS
Quality Review Completed 8/11/2025 CHIHARU SUZUKI
Building Plans Picked Up 8/12/2025 APPLICANT
Applicant returned to address corrections 8/18/2025 JOHN TRIANTAFYLLOS
Applicant returned to address corrections 8/21/2025 JOHN TRIANTAFYLLOS
Plan Check Approved 8/29/2025 CHIHARU SUZUKI
Issued 8/29/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/12/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/13/2025 ABEL CASILLAS
Sewer availability Cleared 8/13/2025 ABEL CASILLAS

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Architect Saadat,, Ariel Jacob; Lic. No.: C41643 6607 LINDENHURST AVE      LOS ANGELES, CA 90048
Contractor Owner-Builder       ,
Engineer Brown,, Patrick John; Lic. No.: C45526 7 STARLING      LAGUNA BEACH, CA 92656

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 10/7/2025 Approved EVAN COOPER
PLUMBING-Rough 10/21/2025 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 11/12/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 11/12/2025 Conditional Approval MICHAEL ALLEN
METHANE-Barrier 11/12/2025 Approved MICHAEL ALLEN
Deputy Steel/Welding 12/17/2025 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Partial Approval ANDREW NAVE
Special/Order Compliance 12/23/2025 Approved DAVID FASTIGGI
Special/Order Compliance 12/23/2025 Conditional Approval DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Partial Approval WILBER ROSALES
Deputy Wood Construction 3/31/2026 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 5/11/2026 Corrections Issued KIRK SANDERS
HVAC-Rough 5/11/2026 Approved KIRK SANDERS
PLUMBING-Rough 5/11/2026 Corrections Issued KIRK SANDERS
Underground Mechanical 5/11/2026 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/14/2026 Not Ready for Inspection WILBER ROSALES
ELECTRICAL-Rough 5/14/2026 Approved WILBER ROSALES
Green Building Rough 5/14/2026 Not Ready for Inspection WILBER ROSALES
Interior/Exterior Lathing 5/14/2026 Corrections Issued WILBER ROSALES
METHANE-Rough 5/14/2026 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 5/14/2026 Approved WILBER ROSALES
Insulation 5/27/2026 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/27/2026 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/1/2026 Approved WILBER ROSALES
Green Building Rough 6/1/2026 Approved WILBER ROSALES
METHANE-Rough 6/1/2026 Approved WILBER ROSALES
Verify Sprinkler Sign Off 6/1/2026 Approved WILBER ROSALES
Shower Pan 6/3/2026 Approved WILBER ROSALES