12326 W MARSHALL ST 90230

Certificate Information: 12326 W MARSHALL ST 90230

Application / Permit
25014-30000-02990
Plan Check / Job No.
B25WL05395
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached Accessory Dwelling Unit per State GC 66323(a)(2)
Permit Issued
Issued on 10/23/2025
Issuing Office
West Los Angeles
Current Status
Issued on 10/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/1/2025 APPLICANT
Assigned to Plan Check Engineer 7/1/2025 HOOMAN HAJIZADEH
Corrections Issued 7/2/2025 HOOMAN HAJIZADEH
Building Plans Picked Up 7/3/2025 APPLICANT
Applicant returned to address corrections 10/21/2025 AMY GUEVARRA
Plan Check Approved 10/23/2025 AMY GUEVARRA
Issued 10/23/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/18/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/18/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/18/2025 BIAINA HARITUNIAN
Sewer availability Cleared 7/18/2025 BIAINA HARITUNIAN
Specific Plan Cleared 7/31/2025 RICHARD WOO
Construction near power lines Cleared 10/2/2025 RIDWAN HARDY

Contact Information

Contractor Forefront Development Inc; Lic. No.: 809468-B 20300 VENTURA STE 215      WOODLAND HILLS, CA 91364
Engineer Kia,, Babak; Lic. No.: C94091 21930 MARYLEE ST APT 87      WOODLAND HILLS, CA 91367

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/4/2025 Corrections Issued WILBER ROSALES
PLUMBING-Rough 12/9/2025 Not Ready for Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 12/10/2025 Corrections Issued WILBER ROSALES
Excavation/Setback/Form/Re-Bar 12/12/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 4/13/2026 Partial Approval ANTHONY EGSON
Green Building Rough 4/13/2026 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 4/13/2026 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 4/24/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Rough 4/29/2026 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 5/7/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Rough 5/7/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Rough 5/12/2026 Approved DAVID FEILER
HVAC-Rough 5/12/2026 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/12/2026 Approved DAVID FEILER
HVAC-Rough 5/27/2026 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Approved DAKOTA LOW
Green Building Rough 6/1/2026 Not Ready for Inspection DAKOTA LOW
Verify Sprinkler Sign Off 6/1/2026 Approved DAKOTA LOW
BUILDING-Rough-Frame 6/5/2026 Not Ready for Inspection MORRIS JACKSON
Green Building Rough 6/5/2026 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 6/5/2026 Approved MORRIS JACKSON