718-718 1/2 W 80TH ST 90044

Certificate Information: 718-718 1/2 W 80TH ST 90044

Application / Permit
25014-30000-02972
Plan Check / Job No.
B25WL05344
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Addition of a storage room in between 2 SFD's creating a duplex. *** 2 of 2 ***
Permit Issued
Issued on 8/21/2025
Issuing Office
Metro
Current Status
CofO Issued on 3/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2025 APPLICANT
Assigned to Plan Check Engineer 7/1/2025 RICHARD GARCIA
Corrections Issued 7/1/2025 RICHARD GARCIA
Building Plans Picked Up 7/7/2025 APPLICANT
Applicant returned to address corrections 7/21/2025 HOOMAN HAJIZADEH
Applicant returned to address corrections 7/22/2025 CAROLEAN BASMA
Plan Check Approved 7/30/2025 JOHN TRIANTAFYLLOS
Issued 8/21/2025 APPLICANT
No Progress 3/15/2026 DEROLD HAUFF
CofO in Progress 3/15/2026 DEROLD HAUFF
CofO in Progress 3/16/2026 JOHN QUINTANILLA
Permit Finaled 3/17/2026 DEROLD HAUFF
CofO Issued 3/17/2026 DEROLD HAUFF
Permit Finaled 3/17/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/21/2025 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/21/2025 BRYAN GODINEZ
Roof/Waste drainage to street Cleared 7/21/2025 BRYAN GODINEZ
"Q" conditions Cleared 7/29/2025 RUBEN VASQUEZ
City Hist. Cultural Monument Cleared 7/29/2025 MELISSA JONES
Historic monument Cleared 7/29/2025 MELISSA JONES

Contact Information

Contractor Mofakham Arash; Lic. No.: 1035634-B 12340 MONTANA AVE UNIT #106      LOS ANGELES, CA 90049
Engineer Aalam,, Yahya; Lic. No.: C94318 3111 4TH ST APT 401      SANTA MONICA, CA 90405

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 9/17/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 9/25/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 9/25/2025 Approved JOHN QUINTANILLA
Wood Frame 10/3/2025 Not Ready for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 10/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 10/7/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 10/10/2025 Approved JOHN QUINTANILLA
Wood Frame 10/10/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 10/15/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Partial Approval JOHN QUINTANILLA
Green Building Rough 10/15/2025 Not Ready for Inspection JOHN QUINTANILLA
Insulation 10/17/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 10/22/2025 Approved ANTHONY RAMOS
Wood Frame 11/5/2025 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Approved JOHN QUINTANILLA
Wood Frame 11/12/2025 Partial Inspection JOHN QUINTANILLA
Drywall Nailing 11/17/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 11/26/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 11/26/2025 Corrections Issued JOHN QUINTANILLA
Final 11/26/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 11/26/2025 Approved JOHN QUINTANILLA
Green Building Rough 11/26/2025 Approved JOHN QUINTANILLA
Smoke Detectors 11/26/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 12/2/2025 Approved JOHN QUINTANILLA
Final 1/21/2026 Conditional Approval JOHN QUINTANILLA
Final 2/10/2026 OK to Issue CofO JOHN QUINTANILLA