10041 S HARVARD BLVD 90047

Certificate Information: 10041 S HARVARD BLVD 90047

Application / Permit
25014-30000-02873
Plan Check / Job No.
B25WL05174
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition to (E) 1-story SFD. All work per WFPP.
Permit Issued
Issued on 7/28/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2025 APPLICANT
Assigned to Plan Check Engineer 6/24/2025 DAVID CASTILLO
Corrections Issued 6/28/2025 DAVID CASTILLO
Building Plans Picked Up 6/30/2025 APPLICANT
Applicant returned to address corrections 7/18/2025 CAROLEAN BASMA
Applicant returned to address corrections 7/24/2025 CAROLEAN BASMA
Plan Check Approved 7/28/2025 CAROLEAN BASMA
Issued 7/28/2025 APPLICANT
CofO in Progress 3/6/2026 SALVADOR MARTINEZ
CofO Issued 3/10/2026 DEROLD HAUFF
Permit Finaled 3/10/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/14/2025 SAFA JAVANMARDI
Sewer availability Cleared 7/14/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/15/2025 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2025 Approved WAYNE REGESTER
METHANE-Barrier 8/5/2025 Approved WAYNE REGESTER
METHANE-Subgrade 8/5/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 8/28/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/28/2025 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/29/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Not Ready for Inspection SALVADOR MARTINEZ
Insulation 9/2/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 10/28/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 10/28/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 10/28/2025 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 10/31/2025 Corrections Issued SALVADOR MARTINEZ
Pre-Inspection 10/31/2025 Partial Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 11/7/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 11/7/2025 Partial Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 12/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 12/8/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 12/16/2025 Conditional Approval SALVADOR MARTINEZ
Green Building Rough 12/16/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 12/16/2025 Approved SALVADOR MARTINEZ
METHANE-Rough 12/16/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 12/16/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 12/29/2025 Approved DEVON JACKSON
Green Building Rough 12/29/2025 Approved DEVON JACKSON
Insulation 12/29/2025 Not Ready for Inspection DEVON JACKSON
Shower Pan 12/29/2025 Approved DEVON JACKSON
Insulation 1/5/2026 Approved SALVADOR MARTINEZ
Drywall Nailing 1/8/2026 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 1/8/2026 Approved SALVADOR MARTINEZ
Final 2/18/2026 Corrections Issued SALVADOR MARTINEZ
Green Building Final 2/18/2026 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 2/18/2026 Approved SALVADOR MARTINEZ
Final 3/2/2026 OK to Issue CofO SALVADOR MARTINEZ
Green Building Final 3/2/2026 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved SALVADOR MARTINEZ