13040 W EVANSTON ST 90049

Certificate Information: 13040 W EVANSTON ST 90049

Application / Permit
25014-30000-02785
Plan Check / Job No.
B25WL05014
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel & addition to existing 2-story SFD with attached grage and basement. Sprinkler throughout.
Permit Issued
Issued on 10/1/2025
Issuing Office
Valley
Current Status
Issued on 10/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 6/19/2025 BEHROUZ KHOKHAR
Corrections Issued 7/1/2025 BEHROUZ KHOKHAR
Quality Review Completed 7/7/2025 CHIHARU SUZUKI
Building Plans Picked Up 7/8/2025 APPLICANT
Applicant returned to address corrections 8/7/2025 BEHROUZ KHOKHAR
Applicant returned to address corrections 9/18/2025 BEHROUZ KHOKHAR
Plan Check Approved 9/25/2025 BEHROUZ KHOKHAR
Issued 10/1/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/18/2025 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 7/19/2025 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 7/21/2025 ABEL CASILLAS
Sewer availability Cleared 7/21/2025 ABEL CASILLAS
Low Impact Development (LID) Cleared 7/24/2025 ERNEST TSE
Specific Plan Cleared 8/4/2025 HAMID GHAEMMAGHAMI
Grading Pre-Inspection Cleared 9/25/2025 CHIHARU SUZUKI

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Voshall Construction Inc; Lic. No.: 920839-B 9909 TOPANGA CANYON #102      CHATSWORTH, CA 91311
Engineer Lycklama,, James Heinz; Lic. No.: L7525 32218 N BIG OAK LN      CASTAIC, CA 91384
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/1/2025 Conditional Approval HERBERT GIRON
Deputy Reinf. Concrete 12/1/2025 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 12/5/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 12/5/2025 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 12/12/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 1/14/2026 Corrections Issued HERBERT GIRON
PLUMBING-Rough 1/14/2026 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/26/2026 Corrections Issued HERBERT GIRON
PLUMBING-Rough 1/26/2026 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 1/28/2026 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 1/28/2026 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 3/19/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 3/19/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 4/28/2026 Partial Approval HERBERT GIRON
Sewer 4/28/2026 Partial Approval HERBERT GIRON
HVAC-Rough 5/4/2026 Partial Inspection HERBERT GIRON
PLUMBING-Rough 6/3/2026 Corrections Issued HERBERT GIRON