4182 S LA SALLE AVE 90062

Certificate Information: 4182 S LA SALLE AVE 90062

Application / Permit
25014-30000-02735
Plan Check / Job No.
B25WL04952
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to the rear of (E) one-story SFD.
Permit Issued
Issued on 7/8/2025
Issuing Office
Metro
Current Status
CofO Issued on 3/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2025 APPLICANT
Assigned to Plan Check Engineer 6/13/2025 JAHANSHAH POURHASSAN
Corrections Issued 6/17/2025 JAHANSHAH POURHASSAN
Building Plans Picked Up 6/18/2025 APPLICANT
Plan Check Approved 7/2/2025 HOOMAN HAJIZADEH
Issued 7/8/2025 APPLICANT
CofO in Progress 1/20/2026 SABAS ALONSO
CofO in Progress 1/20/2026 SABAS ALONSO
CofO in Progress 3/8/2026 SABAS ALONSO
Permit Finaled 3/9/2026 DEROLD HAUFF
CofO Issued 3/9/2026 DEROLD HAUFF
Permit Finaled 3/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/24/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 6/26/2025 DERRICK MAGEE

Contact Information

Contractor 7 Day Builders Inc; Lic. No.: 1106832-B 8929 S SEPULVEDA BLVD STE 403      LOS ANGELES, CA 90045
Engineer Lobnan,, Essam; Lic. No.: C78053 PO BOX 64373      LOS ANGELES, CA 90064

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/11/2025 Corrections Issued SABAS ALONSO
Deputy Drilled-In Anchors 7/14/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 7/16/2025 Corrections Issued SABAS ALONSO
Deputy Drilled-In Anchors 7/25/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 7/29/2025 Corrections Issued SABAS ALONSO
Deputy Drilled-In Anchors 8/4/2025 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 8/7/2025 Approved SABAS ALONSO
Underground Mechanical 8/7/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 9/25/2025 Corrections Issued SABAS ALONSO
PLUMBING-Rough 9/25/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 10/2/2025 Approved SABAS ALONSO
HVAC-Rough 10/2/2025 Approved SABAS ALONSO
PLUMBING-Rough 10/2/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 10/9/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 10/15/2025 Approved SABAS ALONSO
Green Building Rough 10/15/2025 Approved SABAS ALONSO
Insulation 10/15/2025 Corrections Issued SABAS ALONSO
Drywall Nailing 10/20/2025 Approved ANTHONY RAMOS
Insulation 10/20/2025 Approved ANTHONY RAMOS
Final 12/10/2025 Corrections Issued SABAS ALONSO
Green Building Final 12/10/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/10/2025 Corrections Issued SABAS ALONSO
Final 1/16/2026 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Approved SABAS ALONSO
Smoke Detectors 1/16/2026 Approved SABAS ALONSO
Service/Power Release 2/19/2026 Approved SABAS ALONSO
Final 2/24/2026 Corrections Issued SABAS ALONSO
Final 3/6/2026 OK to Issue CofO SABAS ALONSO