2161 S BALSAM AVE 90025

Certificate Information: 2161 S BALSAM AVE 90025

Application / Permit
25014-30000-02733
Plan Check / Job No.
B25WL04945
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-story addition to (e) detached 2-car garage to extend the garage, add storage at 1st floor and add 2nd floor ADU per LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
Permit Issued
Issued on 11/26/2025
Issuing Office
West Los Angeles
Current Status
Issued on 11/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/13/2025 APPLICANT
Assigned to Plan Check Engineer 6/19/2025 REZA HAGHIGHAT
Corrections Issued 6/19/2025 REZA HAGHIGHAT
Building Plans Picked Up 6/25/2025 APPLICANT
Applicant returned to address corrections 8/7/2025 JAHANSHAH POURHASSAN
Plan Check Approved 8/29/2025 HOOMAN HAJIZADEH
Issued 11/26/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 6/30/2025 RICHARD WOO
Address approval Cleared 7/3/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 7/3/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 7/15/2025 COLIN LOREDO
Sewer availability Cleared 7/15/2025 COLIN LOREDO
Grading Pre-Inspection Cleared 8/7/2025 REZA HAGHIGHAT

Contact Information

Contractor Ricard Glenn Construction Inc; Lic. No.: 523293-B 1223 WILSHIRE BLVD #881      PACIFIC PALISADES, CA 90403
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 2/10/2026 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
METHANE-Rough 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 4/3/2026 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 4/8/2026 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 4/8/2026 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2026 Approved CHRISTOPHER WILSON
HVAC-Rough 4/8/2026 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 4/8/2026 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/29/2026 Approved WILBER ROSALES
Green Building Rough 4/29/2026 Approved WILBER ROSALES
HVAC-Rough 4/29/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 4/29/2026 Partial Approval WILBER ROSALES
METHANE-Rough 4/29/2026 Approved WILBER ROSALES
Shower Pan 4/29/2026 Approved WILBER ROSALES
Verify Sprinkler Sign Off 4/29/2026 Approved WILBER ROSALES
Insulation 5/5/2026 Approved RYAN SALAZAR
Drywall Nailing 5/8/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 5/14/2026 Approved DAVID SCANTLIN