1208 N MONUMENT ST 90272

Certificate Information: 1208 N MONUMENT ST 90272

Application / Permit
25014-30000-02674
Plan Check / Job No.
B25WL04820
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
Issued on 7/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/10/2025 APPLICANT
Assigned to Plan Check Engineer 6/11/2025 SELLA BENYAMIN
Corrections Issued 6/17/2025 SELLA BENYAMIN
Quality Review Completed 6/17/2025 STEVEN KIM
Building Plans Picked Up 6/18/2025 APPLICANT
Plan Check Approved 7/11/2025 SELLA BENYAMIN
Issued 7/29/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/16/2025 VISHAL MANDALIA
Sewer availability Cleared 6/16/2025 VISHAL MANDALIA
Roof/Waste drainage to street Cleared 6/20/2025 CELINA MORENO
Hydrant and Access approval Cleared 7/22/2025 KURT CORRAL

Contact Information

Architect Eyster,, Jeffrey Jon; Lic. No.: C35218 7288 SUNSET BLVD #201      LOS ANGELES, CA 90046
Contractor Owner-Builder       ,
Engineer Tuna,, Suleyman; Lic. No.: C73294 3332 BENNETT DRIVE      LOS ANGELES, CA 90068

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2025 Approved MEL KHACHATOURIAN
Deputy Drilled-In Anchors 10/21/2025 Conditional Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 10/27/2025 Partial Approval MEL KHACHATOURIAN
Green Building Rough 10/27/2025 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 10/27/2025 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 12/10/2025 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 2/10/2026 Approved TEMISTOCLES CAAL
PLUMBING-Final 2/10/2026 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 2/10/2026 Approved TEMISTOCLES CAAL
Gas Test 2/11/2026 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Rough 2/11/2026 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/26/2026 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Approved TEMISTOCLES CAAL
Green Building Rough 2/26/2026 Not Ready for Inspection TEMISTOCLES CAAL
Verify Sprinkler Sign Off 2/26/2026 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/11/2026 Approved TEMISTOCLES CAAL
Green Building Rough 3/11/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 3/11/2026 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/31/2026 Approved TEMISTOCLES CAAL
Insulation 3/31/2026 Approved TEMISTOCLES CAAL
Drywall Nailing 4/15/2026 Approved MICHAEL ALLEN
Shower Pan 5/14/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 5/20/2026 Approved TEMISTOCLES CAAL