11870 W JUNIETTE ST 90230

Certificate Information: 11870 W JUNIETTE ST 90230

Application / Permit
25014-30000-02595
Plan Check / Job No.
B25WL04702
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING S.F.D. ALL WORK PER W.F.P.P.
Permit Issued
Issued on 7/24/2025
Issuing Office
West Los Angeles
Current Status
Issued on 7/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/5/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 ALFREDO JARA
Corrections Issued 6/9/2025 ALFREDO JARA
Building Plans Picked Up 6/11/2025 APPLICANT
Applicant returned to address corrections 7/2/2025 CAROLEAN BASMA
Plan Check Approved 7/24/2025 CAROLEAN BASMA
Issued 7/24/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/8/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 7/8/2025 WALLIE JONG
Specific Plan Cleared 7/21/2025 RICHARD WOO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/21/2025 Partial Approval RUBEN RIVAS
Underground Mechanical 8/21/2025 Not Ready for Inspection RUBEN RIVAS
Deputy Drilled-In Anchors 8/27/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 8/27/2025 Approved RUBEN RIVAS
PLUMBING-Rough 9/19/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 9/19/2025 Corrections Issued HERBERT GIRON
Gas Test 9/24/2025 Approved RUBEN RIVAS
PLUMBING-Rough 9/24/2025 Corrections Issued RUBEN RIVAS
Underground Mechanical 9/24/2025 Corrections Issued RUBEN RIVAS
Gas Test 9/29/2025 Approved RUBEN RIVAS
Underground Mechanical 9/29/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Partial Approval HERBERT GIRON
Special/Order Compliance 10/2/2025 Partial Inspection BOBBY KEY
Special/Order Compliance 10/2/2025 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 12/5/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/5/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Approved ANTHONY EGSON
Green Building Rough 12/5/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/5/2025 Approved ANTHONY EGSON
Shower Pan 12/5/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/15/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 12/22/2025 Conditional Approval ANTHONY EGSON
Green Building Rough 12/22/2025 Approved ANTHONY EGSON
Insulation 12/29/2025 Corrections Issued ANTHONY EGSON
Insulation 1/26/2026 Approved ANTHONY EGSON
Insulation 1/28/2026 Approved ANTHONY EGSON
Drywall Nailing 2/4/2026 Approved ANTHONY EGSON
Interior/Exterior Lathing 2/4/2026 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/1/2026 Conditional Approval ANTHONY EGSON
Final 5/1/2026 Corrections Issued ANTHONY EGSON
Green Building Final 5/1/2026 Approved ANTHONY EGSON
MERV13>=Final 5/1/2026 Not Ready for Inspection ANTHONY EGSON
MERV13>=Rough 5/1/2026 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Approved ANTHONY EGSON
Smoke Detectors 5/1/2026 Corrections Issued ANTHONY EGSON
Smoke Detectors 5/7/2026 Approved ANTHONY EGSON