5713 W 75TH ST 90045

Certificate Information: 5713 W 75TH ST 90045

Application / Permit
25014-30000-02553
Plan Check / Job No.
B25WL04616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ADU per state per GC 66323 a 3.
Permit Issued
Issued on 8/4/2025
Issuing Office
Current Status
Issued on 8/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 YASHAR EMAMI
Corrections Issued 6/20/2025 YASHAR EMAMI
Quality Review Completed 6/20/2025 CHIHARU SUZUKI
Building Plans Picked Up 6/24/2025 APPLICANT
Applicant returned to address corrections 7/16/2025 YASHAR EMAMI
Plan Check Approved 7/23/2025 YASHAR EMAMI
Issued 8/4/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/28/2025 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 6/28/2025 KIMBERLY HERNANDEZ
Specific Plan Cleared 7/1/2025 RICHARD WOO
Eng Process Fee Ord 176,300 Cleared 7/10/2025 ADRIAN SANCHEZ
Permit Cleared 7/10/2025 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 7/23/2025 YASHAR EMAMI

Contact Information

Contractor Sgh Development Inc; Lic. No.: 1119303-B 6653 SHIRLEY AV      RESEDA, CA 91335

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/13/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 8/15/2025 Approved MICHAEL ALLEN
Special/Order Compliance 8/15/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 8/27/2025 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 9/2/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 9/3/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 1/8/2026 Not Ready for Inspection HERBERT GIRON
Special/Order Compliance 1/8/2026 Corrections Issued HERBERT GIRON
HVAC-Rough 2/18/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 2/23/2026 Corrections Issued JESUS PINEDA
Green Building Rough 2/23/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 2/23/2026 Partial Approval JESUS PINEDA
MERV13>=Rough 2/23/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 2/24/2026 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Approved HERBERT GIRON
Insulation 2/24/2026 Approved HERBERT GIRON
Special/Order Compliance 2/24/2026 Partial Inspection TEMISTOCLES CAAL
Drywall Nailing 2/26/2026 Approved JESUS PINEDA
Shower Pan 3/3/2026 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 3/16/2026 Approved HERBERT GIRON
Sewer 5/7/2026 Approved JESUS PINEDA
Underground Mechanical 5/7/2026 Approved JESUS PINEDA