17042 W BOLLINGER DR 90272
Certificate Information: 17042 W BOLLINGER DR 90272
- Application / Permit
- 25014-30000-02545
- Plan Check / Job No.
- B25WL04602
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND BASEMENT, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT SOLAR INSTALLATION EXEMPT PER GOVERNOR'S EO N-29-25
- Permit Issued
- Issued on 10/31/2025
- Issuing Office
- Current Status
- Issued on 10/31/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | VIVIAN LAO |
| Corrections Issued | 6/17/2025 | VIVIAN LAO |
| Quality Review Completed | 6/17/2025 | JOHN FRANCIA |
| Building Plans Picked Up | 6/26/2025 | APPLICANT |
| Applicant returned to address corrections | 7/24/2025 | VIVIAN LAO |
| Plan Check Approved | 9/3/2025 | VIVIAN LAO |
| Issued | 10/31/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/1/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | DAVID LOPEZ |
| Hydrant and Access approval | Cleared | 7/22/2025 | RUEL COLE |
Contact Information
| Contractor | Mega Builders Inc; Lic. No.: 898347-B | 18375 VENTURA BLVD SUITE 520 TARZANA, CA 91356 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/10/2025 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/10/2025 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/8/2026 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 5/8/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 5/8/2026 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 5/8/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/21/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 5/29/2026 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 5/29/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 5/29/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/29/2026 | Approved | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 5/29/2026 | Approved | MICHAEL ALLEN |