5348 W THORNBURN ST 90045

Certificate Information: 5348 W THORNBURN ST 90045

Application / Permit
25014-30000-02424
Plan Check / Job No.
B25WL04366
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) 1 story SFD. Convert existing portion of house into attached 1 car garage. 1 of 2
Permit Issued
Issued on 8/27/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2025 APPLICANT
Assigned to Plan Check Engineer 5/29/2025 BEHROUZ KHOKHAR
Corrections Issued 6/6/2025 YASHAR EMAMI
Quality Review Completed 6/9/2025 CHIHARU SUZUKI
Building Plans Picked Up 6/10/2025 APPLICANT
Applicant returned to address corrections 8/13/2025 YASHAR EMAMI
Applicant returned to address corrections 8/20/2025 YASHAR EMAMI
Plan Check Approved 8/27/2025 YASHAR EMAMI
Issued 8/27/2025 APPLICANT
CofO in Progress 2/12/2026 JESUS PINEDA
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/5/2025 YASHAR EMAMI
Address approval Cleared 6/11/2025 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 6/12/2025 XOCHITL ARQUIETA
Sewer availability Cleared 6/12/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 6/30/2025 HISASHI KOBAYAKAWA
Specific Plan Cleared 7/24/2025 PEDRO AYALA
GPI Written Notices Cleared 8/27/2025 YASHAR EMAMI

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Adler,, Neal; Lic. No.: C84772 2220 EXPOSITION DR 60      SAN LUIS OBISPO, CA 93401

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/8/2025 Corrections Issued JESUS PINEDA
Pre-Inspection 9/8/2025 Approved JESUS PINEDA
Deputy Drilled-In Anchors 9/17/2025 Approved JESUS PINEDA
Excavation/Setback/Form/Re-Bar 9/17/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 9/17/2025 Corrections Issued JESUS PINEDA
Special/Order Compliance 9/17/2025 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 10/1/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 10/1/2025 Approved JESUS PINEDA
PLUMBING-Rough 10/1/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Corrections Issued HERBERT GIRON
Special/Order Compliance 10/3/2025 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved JESUS PINEDA
Deputy Wood Construction 11/13/2025 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 11/17/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/17/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 11/17/2025 Approved JESUS PINEDA
Shower Pan 11/17/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/24/2025 Approved RUBEN RIVAS
HVAC-Rough 11/24/2025 Partial Approval RUBEN RIVAS
Interior/Exterior Lathing 11/24/2025 Not Ready for Inspection RUBEN RIVAS
BUILDING-Rough-Frame 11/26/2025 Not Ready for Inspection JESUS PINEDA
Green Building Rough 11/26/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 11/26/2025 Partial Approval JESUS PINEDA
Insulation 12/9/2025 Corrections Issued JESUS PINEDA
Insulation 12/11/2025 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 12/15/2025 Approved JESUS PINEDA
Drywall Nailing 12/15/2025 Approved JESUS PINEDA
Insulation 12/15/2025 Approved JESUS PINEDA
MERV13>=Rough 12/15/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 12/17/2025 Approved JESUS PINEDA
ELECTRICAL-Final 2/4/2026 Approved JESUS PINEDA
Service/Power Release 2/4/2026 Approved JESUS PINEDA
Final 2/10/2026 Corrections Issued JESUS PINEDA
Green Building Final 2/10/2026 Approved JESUS PINEDA
HVAC-Final 2/10/2026 Approved JESUS PINEDA
MERV13>=Final 2/10/2026 Approved JESUS PINEDA
PLUMBING-Final 2/10/2026 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/10/2026 SGSOV Approved JESUS PINEDA
Smoke Detectors 2/10/2026 Approved JESUS PINEDA
Final 2/12/2026 OK to Issue CofO JESUS PINEDA