12324 W MARSHALL ST 90230
Certificate Information: 12324 W MARSHALL ST 90230
- Application / Permit
- 25014-30000-02067
- Plan Check / Job No.
- B25WL03783
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodeling and 2nd story addition to (e) 1 story S.F.D.
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | ZENA HADDIS |
| Corrections Issued | 6/13/2025 | ZENA HADDIS |
| Quality Review Completed | 6/18/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/20/2025 | APPLICANT |
| Plan Check Approved | 7/17/2025 | ZENA HADDIS |
| Issued | 7/17/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/15/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 7/15/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Forefront Development Inc; Lic. No.: 809468-B | 20300 VENTURA STE 215 WOODLAND HILLS, CA 91364 |
| Engineer | Kia,, Babak; Lic. No.: C94091 | 21930 MARYLEE ST APT 87 WOODLAND HILLS, CA 91367 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Rough | 6/8/2026 |
| Sewer | 6/8/2026 |
| PLUMBING-Rough | 6/8/2026 |
| HVAC-Rough | 6/8/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2025 | Not Ready for Inspection | WILBER ROSALES |
| Footing/Foundation/Slab | 12/22/2025 | Not Ready for Inspection | WILBER ROSALES |
| Footing/Foundation/Slab | 2/2/2026 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/9/2026 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/12/2026 | Approved | ANTHONY EGSON |
| Deputy Reinf. Concrete | 2/13/2026 | Conditional Approval | DAVID FEILER |
| Special/Order Compliance | 2/25/2026 | Partial Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2026 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 3/17/2026 | Partial Approval | ANTHONY EGSON |
| Insulation | 3/20/2026 | Partial Approval | DAKOTA LOW |
| Deputy Steel/Welding | 4/14/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Corrections Issued | DAKOTA LOW |
| Green Building Rough | 5/19/2026 | Not Ready for Inspection | DAKOTA LOW |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Rough | 5/28/2026 | Not Ready for Inspection | MORRIS JACKSON |