6621 W 88TH PL 1-2 90045
Certificate Information: 6621 W 88TH PL 1-2 90045
- Application / Permit
- 25014-30000-01900
- Plan Check / Job No.
- B25WL03467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2story addition to exsiting detached garage. Addition of ADU PER ordinance LAMC 12.22 A.33(c) AND (d) at the first floor and add SB-9 unit to new 2nd floor.
- Permit Issued
- Issued on 2/17/2026
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/17/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2025 | YASHAR EMAMI |
| Corrections Issued | 5/22/2025 | YASHAR EMAMI |
| Quality Review Completed | 6/3/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/5/2025 | APPLICANT |
| Plan Check Approved | 12/12/2025 | YASHAR EMAMI |
| Issued | 2/17/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 6/13/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/18/2025 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 6/18/2025 | RICHARD WOO |
| Specific Plan | Cleared | 7/15/2025 | ROSALINDA MEZA |
| ZI | Cleared | 7/15/2025 | ROSALINDA MEZA |
| Construction near power lines | Cleared | 8/13/2025 | RIDWAN HARDY |
| Senate Bill 9 | Cleared | 9/12/2025 | ROSALINDA MEZA |
| Hold | Cleared | 5/28/2026 | MARIA VENDIVIL |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | John Williamson Construction Inc; Lic. No.: 451421-B | 8723 BLERIOT AVE LOS ANGELES, CA 90045 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/23/2026 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 2/23/2026 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 2/25/2026 | Partial Approval | JESUS PINEDA |
| Rough-Elec/Plmb/HVAC | 6/1/2026 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/29/2026 | Approved | MICHAEL LEWIS |
| Green Building Rough | 6/29/2026 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 6/29/2026 | Approved | MICHAEL LEWIS |
| Insulation | 7/7/2026 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/9/2026 | Approved | EUGENE CASSIDY |
| Insulation | 7/9/2026 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/22/2026 | Approved | MICHAEL LEWIS |